Asset Retirement Obligations
6 Months Ended
Jun. 30, 2018
Asset Retirement Obligation [Abstract]  
Asset Retirement Obligations
ASSET RETIREMENT OBLIGATIONS

FirstEnergy has recognized applicable legal obligations for AROs and their associated cost, primarily for the decommissioning of the TMI-2 nuclear generating facility and environmental remediation, including reclamation of sludge disposal ponds, closure of coal ash disposal sites, underground and above-ground storage tanks and wastewater treatment lagoons. In addition, FirstEnergy has recognized conditional retirement obligations, primarily for asbestos remediation.

FirstEnergy uses an expected cash flow approach to measure the fair value of the nuclear decommissioning and environmental remediation AROs, considering the expected timing of settlement of the ARO based on the expected economic useful life of the plants. Conditional retirement obligations associated with tangible long-lived assets are recognized at fair value in the period in which they are incurred if a reasonable estimate can be made, even though there may be uncertainty about timing or method of settlement.

The aggregate ARO liabilities for FirstEnergy are approximately $589 million and $570 million as of June 30, 2018 and December 31, 2017, respectively.

In April 2015, the EPA finalized regulations for the disposal of CCRs (non-hazardous), establishing national standards for landfill design, structural integrity design and assessment criteria for surface impoundments, groundwater monitoring and protection procedures and other operational and reporting procedures to assure the safe disposal of CCRs from electric generating plants. On September 13, 2017, the EPA announced that it would reconsider certain provisions of the final regulations. On July 17, 2018, the EPA Administrator signed a final rule extending the deadline for certain CCR facilities to cease disposal and commence closure activities, as well as, establishing less stringent groundwater monitoring and protection requirements. Based on an assessment of the finalized regulations, the future cost of compliance and expected timing had no significant impact on FirstEnergy's existing AROs associated with CCRs. Although not currently expected, changes in timing and closure plan requirements in the future could materially and adversely impact FirstEnergy's AROs.