Regulatory Matters
12 Months Ended
Dec. 31, 2011
Regulated Operations [Abstract]  
Regulatory Matters
REGULATORY MATTERS

RELIABILITY MATTERS

Federally-enforceable mandatory reliability standards apply to the bulk electric system and impose certain operating, record-keeping and reporting requirements on the Utilities, FES, AE Supply, FGCO, FENOC, ATSI and TrAIL. The NERC is the ERO designated by FERC to establish and enforce these reliability standards, although NERC has delegated day-to-day implementation and enforcement of these reliability standards to eight regional entities, including RFC. All of FirstEnergy's facilities are located within the RFC region. FirstEnergy actively participates in the NERC and RFC stakeholder processes, and otherwise monitors and manages its companies in response to the ongoing development, implementation and enforcement of the reliability standards implemented and enforced by the RFC.

FirstEnergy believes that it is in compliance with all currently-effective and enforceable reliability standards. Nevertheless, in the course of operating its extensive electric utility systems and facilities, FirstEnergy occasionally learns of isolated facts or circumstances that could be interpreted as excursions from the reliability standards. If and when such items are found, FirstEnergy develops information about the item and develops a remedial response to the specific circumstances, including in appropriate cases “self-reporting” an item to RFC. Moreover, it is clear that the NERC, RFC and FERC will continue to refine existing reliability standards as well as to develop and adopt new reliability standards. The financial impact of complying with future new or amended standards cannot be determined at this time; however, 2005 amendments to the FPA provide that all prudent costs incurred to comply with the future reliability standards be recovered in rates. Any future inability on FirstEnergy's part to comply with the reliability standards for its bulk power system could result in the imposition of financial penalties that could have a material adverse effect on its financial condition, results of operations and cash flows.

On December 9, 2008, a transformer at JCP&L's Oceanview substation failed, resulting in an outage on certain bulk electric system (transmission voltage) lines out of the Oceanview and Atlantic substations resulting in customers losing power for up to eleven hours. On March 31, 2009, the NERC initiated a Compliance Violation Investigation in order to determine JCP&L's contribution to the electrical event and to review any potential violation of NERC Reliability Standards associated with the event. NERC has submitted first and second Requests for Information regarding this and another related matter. JCP&L is complying with these requests. JCP&L is not able to predict what actions, if any, the NERC may take with respect to this matter.

On August 23, 2010, FirstEnergy self-reported to RFC a vegetation encroachment event on a Met-Ed 230 kV line. This event did not result in a fault, outage, operation of protective equipment, or any other meaningful electric effect on any FirstEnergy transmission facilities or systems. On August 25, 2010, RFC issued a notice of enforcement to investigate the incident. FirstEnergy submitted a data response to RFC on September 27, 2010. On July 8, 2011, RFC and Met-Ed signed a settlement agreement to resolve all outstanding issues related to the vegetation encroachment event. The settlement calls for Met-Ed to pay a penalty of $650,000, and for FirstEnergy to perform certain mitigating actions. These mitigating actions include inspecting FirstEnergy's transmission system using LiDAR technology, and reporting the results of inspections, and any follow-up work, to RFC. FirstEnergy was performing the LiDAR work in response to certain other industry directives issued by NERC in 2010. NERC subsequently approved the settlement agreement and, on September 30, 2011, submitted the approved settlement to FERC for final approval. FERC approved the settlement agreement on October 28, 2011. Met-Ed subsequently paid the $650,000 penalty and, on December 31, 2011, RFC sent written notice that this matter has been closed.

In 2011, RFC performed routine compliance audits of parts of FirstEnergy's bulk-power system and generally found the audited systems and process to be in full compliance with all audited reliability standards. RFC will perform additional audits in 2012.

MARYLAND
By statute enacted in 2007, the obligation of Maryland utilities to provide SOS to residential and small commercial customers, in exchange for recovery of their costs plus a reasonable profit, was extended indefinitely. The legislation also established a 5-year cycle (to begin in 2008) for the MDPSC to report to the legislature on the status of SOS. PE now conducts rolling auctions to procure the power supply necessary to serve its customer load pursuant to a plan approved by the MDPSC. However, the terms on which PE will provide SOS to residential customers after the current settlement expires at the end of 2012 will depend on developments with respect to SOS in Maryland over the coming year, including but not limited to, possible MDPSC decisions in the proceedings discussed below.

The MDPSC opened a new docket in August 2007 to consider matters relating to possible “managed portfolio” approaches to SOS and other matters. “Phase II” of the case addressed utility purchases or construction of generation, bidding for procurement of demand response resources and possible alternatives if the TrAIL and PATH projects were delayed or defeated. It is unclear when the MDPSC will issue its findings in this proceeding.
In September 2009, the MDPSC opened a new proceeding to receive and consider proposals for construction of new generation resources in Maryland. In December 2009, Governor Martin O'Malley filed a letter in this proceeding in which he characterized the electricity market in Maryland as a “failure” and urged the MDPSC to use its existing authority to order the construction of new generation in Maryland, vary the means used by utilities to procure generation and include more renewables in the generation mix. In December 2010, the MDPSC issued an order soliciting comments on a model RFP for solicitation of long-term energy commitments by Maryland electric utilities. PE and numerous other parties filed comments, and on September 29, 2011, the MDPSC issued an order requiring the utilities to issue the RFP crafted by the MDPSC by October 7, 2011. The RFPs were issued by the utilities as ordered by the MDPSC. The order, as amended, indicated that bids were due by January 20, 2012, and that the MDPSC would be the entity evaluating all bids. The Chairman of the MDPSC has stated publicly that several bids were received, but no other information was released. After receipt of further comments from interested parties, including PE, on January 13, 2012, a hearing on whether more generation is needed, irrespective of what bids may have been received, was held on January 31, 2012. There has been no further action on this matter.

In September 2007, the MDPSC issued an order that required the Maryland utilities to file detailed plans for how they will meet the “EmPOWER Maryland” proposal that electric consumption be reduced by 10% and electricity demand be reduced by 15%, in each case by 2015.

The Maryland legislature in 2008 adopted a statute codifying the EmPOWER Maryland goals. In 2008, PE filed its comprehensive plans for attempting to achieve those goals, asking the MDPSC to approve programs for residential, commercial, industrial, and governmental customers, as well as a customer education program. The MDPSC ultimately approved the programs in August 2009 after certain modifications had been made as required by the MDPSC, and approved cost recovery for the programs in October 2009. Expenditures were estimated to be approximately $101 million for the PE programs for the period of 2009 to 2015 and would be recovered over that six year period. Meanwhile, after extensive meetings with the MDPSC Staff and other stakeholders, PE's plans for additional and improved programs for the period 2012-2014 were filed on August 31, 2011. The MDPSC held hearings on PE's and the other utilities' plans in October 2011, and on December 22, 2011, issued an order approving Potomac Edison's plan with various modifications and follow-up assignments. On January 23, 2012, PE filed a Request for Rehearing because additional facts not considered by the MDPSC demonstrate, among other things, that conservation voltage reduction program expenditures should be accorded cost recovery through the EmPOWER surcharge, as has been provided for all other EmPOWER programs as opposed to recovery of those expenditures being addressed in a future base rate case as the MDPSC found in its order.
In March 2009, the MDPSC issued an order temporarily suspending the right of all electric and gas utilities in the state to terminate service to residential customers for non-payment of bills. The MDPSC subsequently issued an order making various rule changes relating to terminations, payment plans, and customer deposits that make it more difficult for Maryland utilities to collect deposits or to terminate service for non-payment. The MDPSC is continuing to collect data on payment plan and related issues and has adopted regulations that expand the summer and winter “severe weather” termination moratoria when temperatures are very high or very low, from one day, as provided by statute, to three days on each occurrence.
The Maryland legislature passed a bill on April 11, 2011, which requires the MDPSC to promulgate rules by July 1, 2012 that address service interruptions, downed wire response, customer communication, vegetation management, equipment inspection, and annual reporting. In crafting the regulations, the legislation directs the MDPSC to consider cost-effectiveness, and provides that the MDPSC may adopt different standards for different utilities based on such factors as system design and existing infrastructure, geography, and customer density. Beginning in July 2013, the MDPSC is required to assess each utility's compliance with the new rules, and may assess penalties of up to $25,000 per day per violation. The MDPSC convened a working group of utilities, regulators, and other interested stakeholders to address the topics of the proposed rules. A draft of the rules was filed, along with the report of the working group, on October 27, 2011. Hearings to consider the rules and comments occurred over four days between December 8 and 15, 2011, after which revised rules were sent for legislative review. The proposed rules were published in the Maryland Register on February 24, 2012, and a deadline of March 26, 2012, was set for the filing of further comments. A further hearing is required before the rules could become final. Separately, on July 7, 2011, the MDPSC adopted draft rules requiring monitoring and inspections for contact voltage. The draft rules were published in September, 2011. After a further hearing in October, 2011, the final rules were re-published and became effective on November 28, 2011.

NEW JERSEY

On September 8, 2011, the Division of Rate Counsel filed a Petition with the NJBPU asserting that it has reason to believe that JCP&L is earning an unreasonable return on its New Jersey jurisdictional rate base. The Division of Rate Counsel requests that the NJBPU order JCP&L to file a base rate case petition so that the NJBPU may determine whether JCP&L's current rates for electric service are just and reasonable. JCP&L filed an answer to the Petition on September 28, 2011, stating, inter alia, that the Division of Rate Counsel analysis upon which it premises its Petition contains errors and inaccuracies, that JCP&L's achieved return on equity is currently within a reasonable range, and that there is no reason for the NJBPU to require JCP&L to file a base rate case at this time. On November 30, 2011, the NJBPU ordered that the matter be assigned to the NJBPU President to act as presiding officer to set and modify the schedule for this matter as appropriate, decide upon motions, and otherwise control the conduct of this case, without the need for full Board approval. The matter is pending and a schedule for further proceedings has not yet been established.

On September 22, 2011, the NJBPU ordered that JCP&L hire a Special Reliability Master, subject to NJBPU approval, to evaluate JCP&L's design, operating, maintenance and performance standards as they pertain to the Morristown, New Jersey underground electric distribution system, and make recommendations to JCP&L and the NJBPU on the appropriate courses of action necessary to ensure adequate reliability and safety in the Morristown underground network. On October 12, 2011, the Special Reliability Master was selected and on January 31, 2012, the project report was submitted to the Company and NJBPU Staff. On February 10, 2012, the NJBPU accepted the report and directed the Staff to present recommendations on March 12, 2012, on actions required by JCP&L to ensure the safe, reliable operation of the Morristown network.

Pursuant to a formal Notice issued by the NJBPU on September 14, 2011, public hearings were held on September 26 and 27, 2011, to solicit public comments regarding the state of preparedness and responsiveness of the local electric distribution companies prior to, during and after Hurricane Irene. By subsequent Notice issued September 28, 2011, additional hearings were held in October 2011. Additionally, the NJBPU accepted written comments through October 31, 2011 related to this inquiry. On December 4, 2011, the NJBPU Division of Reliability and Security issued a Request for Qualifications soliciting bid proposals from qualified consulting firms to provide expertise in the review and evaluation of New Jersey's electric distribution companies' preparation and restoration to Hurricane Irene and the October 2011 snowstorm. Responsive bids were submitted on January 20, 2012, and the report of selected bidder is to be submitted to the NJPBU 120 days from the date the contract is awarded. On December 14, 2011, the NJBPU Staff filed a report of its preliminary findings and recommendations with respect to the electric utility companies' planning and response to Hurricane Irene and the October 2011 snowstorm. The NJBPU has not indicated what additional action, if any, may be taken as a result of information obtained through this process.

OHIO

The Ohio Companies operate under an ESP, which expires on May 31, 2014. The material terms of the ESP include: generation supplied through a CBP commencing June 1, 2011; a load cap of no less than 80%, which also applies to tranches assigned post-auction; a 6% generation discount to certain low income customers provided by the Ohio Companies through a bilateral wholesale contract with FES (FES is one of the wholesale suppliers to the Ohio Companies); no increase in base distribution rates through May 31, 2014; and a new distribution rider, Rider DCR, to recover a return of, and on, capital investments in the delivery system. The Ohio Companies also agreed not to recover from retail customers certain costs related to transmission cost allocations by PJM as a result of ATSI's integration into PJM for the longer of the five-year period from June 1, 2011 through May 31, 2015 or when the amount of costs avoided by customers for certain types of products totals $360 million dependent on the outcome of certain PJM proceedings, agreed to establish a $12 million fund to assist low income customers over the term of the ESP and agreed to additional matters related to energy efficiency and alternative energy requirements.

Under the provisions of SB221, the Ohio Companies are required to implement energy efficiency programs that will achieve a total annual energy savings equivalent to approximately 166,000 MWH in 2009, 290,000 MWH in 2010, 410,000 MWH in 2011, 470,000 MWH in 2012 and 530,000 MWH in 2013, with additional savings required through 2025. Utilities were also required to reduce peak demand in 2009 by 1%, with an additional 0.75% reduction each year thereafter through 2018.

In December 2009, the Ohio Companies filed the required three year portfolio plan seeking approval for the programs they intend to implement to meet the energy efficiency and peak demand reduction requirements for the 2010-2012 period. The Ohio Companies expect that all costs associated with compliance will be recoverable from customers in 2012. The PUCO issued an Opinion and Order generally approving the Ohio Companies' three-year plan, and the Ohio Companies are in the process of implementing those programs included in the Plan. OE fell short of its statutory 2010 energy efficiency and peak demand reduction benchmarks and therefore, on January 11, 2011, it requested that its 2010 energy efficiency and peak demand reduction benchmarks be amended to actual levels achieved in 2010. Moreover, because the PUCO indicated, when approving the 2009 benchmark request, that it would modify the Ohio Companies' 2010 (and 2011 and 2012) energy efficiency benchmarks when addressing the portfolio plan, the Ohio Companies were not certain of their 2010 energy efficiency obligations. Therefore, CEI and TE (each of which achieved its 2010 energy efficiency and peak demand reduction statutory benchmarks) also requested an amendment if and only to the degree one was deemed necessary to bring them into compliance with their yet-to-be-defined modified benchmarks. On May 19, 2011, the PUCO granted the request to reduce the 2010 energy efficiency and peak demand reductions to the level achieved in 2010 for OE, while finding that the motion was moot for CEI and TE. On June 2, 2011, the Ohio Companies filed an application for rehearing to clarify the decision related to CEI and TE. On July 27, 2011, the PUCO denied that application for rehearing, but clarified that CEI and TE could apply for an amendment in the future for the 2010 benchmarks should it be necessary to do so. Failure to comply with the benchmarks or to obtain such an amendment may subject the Ohio Companies to an assessment of a penalty by the PUCO. In addition to approving the programs included in the plan, with only minor modifications, the PUCO authorized the Ohio Companies to recover all costs related to the original CFL program that the Ohio Companies had previously suspended at the request of the PUCO. Applications for Rehearing were filed by the Ohio Companies, Ohio Energy Group and Nucor Steel Marion, Inc. on April 22, 2011, regarding portions of the PUCO's decision, including the method for calculating savings and certain changes made by the PUCO to specific programs. On September 7, 2011, the PUCO denied those applications for rehearing. The PUCO also included a new standard for compliance with the statutory energy efficiency benchmarks by requiring electric distribution companies to offer “all available cost effective energy efficiency opportunities” regardless of their level of compliance with the benchmarks as set forth in the statute. On October 7, 2011, the Ohio Companies, the Industrial Energy Users - Ohio, and the Ohio Energy Group filed applications for rehearing, arguing that the PUCO'S new standard is unlawful. The Ohio Companies also asked the PUCO to withdraw its amendment of CEI's and TE's 2010 energy efficiency benchmarks. The PUCO did not rule on the Applications for Rehearing within thirty days, thus denying them by operation of law. On December 30, 2011, the Ohio Companies filed a notice of appeal with the Supreme Court of Ohio, challenging the PUCO's new standard. No procedural schedule has been established.

Additionally, under SB221, electric utilities and electric service companies are required to serve part of their load in 2011 from renewable energy resources equivalent to 1.00% of the average of the KWH they served in 2008-2010; in 2012 from renewable energy resources equivalent to 1.50% of the average of the KWH they served in 2009-2011; and in 2013 from renewable energy resources equivalent to 2.00% of the average of the KWH they served in 2010-2012. In August and October 2009, the Ohio Companies conducted RFPs to secure RECs. The RECs acquired through these two RFPs were used to help meet the renewable energy requirements established under SB221 for 2009, 2010 and 2011. In March 2010, the PUCO found that there was an insufficient quantity of solar energy resources reasonably available in the market and reduced the Ohio Companies' aggregate 2009 benchmark to the level of SRECs the Ohio Companies acquired through their 2009 RFP processes, provided the Ohio Companies' 2010 alternative energy requirements be increased to include the shortfall for the 2009 solar REC benchmark. On April 15, 2011, the Ohio Companies filed an application seeking an amendment to each of their 2010 alternative energy requirements for solar RECs generated in Ohio on the basis that an insufficient quantity of solar resources are available in the market but reflecting solar RECs that they have obtained and providing additional information regarding efforts to secure solar RECs. On August 3, 2011, the PUCO granted the Ohio Companies' force majeure request for 2010 and increased their 2011 benchmark by the amount of SRECs generated in Ohio that the Ohio Companies were short in 2010. On September 2, 2011, the Environmental Law and Policy Center and Nucor Steel Marion, Inc. filed applications for rehearing. The Ohio Companies filed their response on September 12, 2011. These applications for rehearing were denied by the PUCO on September 20, 2011, but as part of its Entry on Rehearing the PUCO opened a new docket to review the Ohio Companies' alternative energy recovery rider. Separately, one party has filed a request that the PUCO audit the cost of the Ohio Companies' compliance with the alternative energy requirements and the Ohio Companies' compliance with Ohio law. The PUCO selected auditors to perform a financial and a management audit, and final audit reports are to be filed with the PUCO by May 15, 2012. In August 2011, the Ohio Companies conducted two RFP processes to obtain RECs to meet the statutory benchmarks for 2011 and beyond.

PENNSYLVANIA
The PPUC entered an Order on March 3, 2010 that denied the recovery of marginal transmission losses through the TSC rider for the period of June 1, 2007 through March 31, 2008, directed Met-Ed and Penelec to submit a new tariff or tariff supplement reflecting the removal of marginal transmission losses from the TSC, and instructed Met-Ed and Penelec to work with the various intervening parties to file a recommendation to the PPUC regarding the establishment of a separate account for all marginal transmission losses collected from customers plus interest to be used to mitigate future generation rate increases beginning January 1, 2011. In March 2010, Met-Ed and Penelec filed a Petition with the PPUC requesting that it stay the portion of the March 3, 2010 Order requiring the filing of tariff supplements to end collection of costs for marginal transmission losses. The PPUC granted the requested stay until December 31, 2010. Pursuant to the PPUC's order, Met-Ed and Penelec filed plans to establish separate accounts for marginal transmission loss revenues and related interest and carrying charges. Pursuant to the plan approved by the PPUC, Met-Ed and Penelec began to refund those amounts to customers in January 2011, and the refunds are continuing over a 29 month period until the full amounts previously recovered for marginal transmission loses are refunded. In April 2010, Met-Ed and Penelec filed a Petition for Review with the Commonwealth Court of Pennsylvania appealing the PPUC's March 3, 2010 Order. On June 14, 2011, the Commonwealth Court issued an opinion and order affirming the PPUC's Order to the extent that it holds that line loss costs are not transmission costs and, therefore, the approximately $254 million in marginal transmission losses and associated carrying charges for the period prior to January 1, 2011, are not recoverable under Met-Ed's and Penelec's TSC riders. Met-Ed and Penelec filed a Petition for Allowance of Appeal with the Pennsylvania Supreme Court and also a complaint seeking relief in the U.S. District Court for the Eastern District of Pennsylvania, which was subsequently amended. The PPUC filed a Motion to Dismiss Met-Ed's and Penelec's Amended Complaint on September 15, 2011. Met-Ed and Penelec filed a Responsive brief in Opposition to the PPUC's Motion to Dismiss on October 11, 2011. Although the ultimate outcome of this matter cannot be determined at this time, Met-Ed and Penelec believe that they should ultimately prevail through the judicial process and therefore expect to fully recover the approximately $254 million ($189 million for Met-Ed and $65 million for Penelec) in marginal transmission losses for the period prior to January 1, 2011.

In each of May 2008, 2009 and 2010, the PPUC approved Met-Ed's and Penelec's annual updates to their TSC rider for the annual periods between June 1, 2008 to December 31, 2010, including marginal transmission losses as approved by the PPUC, although the recovery of marginal losses will be subject to the outcome of the proceeding related to the 2008 TSC filing as described above. The PPUC's approval in May 2010 authorized an increase to the TSC for Met-Ed's customers to provide for full recovery by December 31, 2010.

In February 2010, Penn filed a Petition for Approval of its DSP for the period June 1, 2011 through May 31, 2013. In July 2010, the parties to the proceeding filed a Joint Petition for Settlement of all issues. Although the PPUC's Order approving the Joint Petition held that the provisions relating to the recovery of MISO exit fees and one-time PJM integration costs (resulting from Penn's June 1, 2011 exit from MISO and integration into PJM) were approved, it made such provisions subject to the approval of cost recovery by FERC. Therefore, Penn may not put these provisions into effect until FERC has approved the recovery and allocation of MISO exit fees and PJM integration costs.

Pennsylvania adopted Act 129 in 2008 to address issues such as: energy efficiency and peak load reduction; generation procurement; time-of-use rates; smart meters; and alternative energy. Among other things, Act 129 required utilities to file with the PPUC an energy efficiency and peak load reduction plan, (EE&C Plan), by July 1, 2009, setting forth the utilities' plans to reduce energy consumption by a minimum of 1% and 3% by May 31, 2011 and May 31, 2013, respectively, and to reduce peak demand by a minimum of 4.5% by May 31, 2013. Act 129 provides for potentially significant financial penalties to be assessed upon utilities that fail to achieve the required reductions in consumption and peak demand. Act 129 also required utilities to file a SMIP with the PPUC.

The PPUC entered an Order in February 2010 giving final approval to all aspects of the EE&C Plans of Met-Ed, Penelec and Penn and the tariff rider became effective March 1, 2010. On February 18, 2011, the companies filed a petition to approve their First Amended EE&C Plans. On June 28, 2011, a hearing on the petition was held before an ALJ. On December 15, 2011, the ALJ recommended that the amended plans be approved as proposed, and on January 12, 2012, the Commission approved the plans.
WP filed its original EE&C Plan in June 2009, which the PPUC approved, in large part, by Opinion and Order entered in October 2009. In September 2010, WP filed an amended EE&C Plan that is less reliant on smart meter deployment, which the PPUC approved in January 2011.
On August 9, 2011, WP filed a petition to approve its Second Amended EE&C Plan. The proposed Second Revised Plan includes measures and a new program and implementation strategies consistent with the successful EE&C programs of Met-Ed, Penelec and Penn that are designed to enable WP to achieve the post-2011 Act 129 EE&C requirements. On January 6, 2012, a Joint Petition for Settlement of all issues was filed by the parties to the proceeding.

The Pennsylvania Companies submitted a preliminary report on July 15, 2011, and a final report on November 15, 2011, in which they reported on their compliance with statutory May 31, 2011, energy efficiency benchmarks. Met-Ed, Penelec and Penn achieved the 2011 benchmarks; however WP has been unable to provide final results because several customers are still accumulating necessary documentation for projects that may qualify for inclusion in the final results. Preliminary numbers indicate that WP did not achieve its 2011 benchmark and it is not known at this time whether WP will be subject to a fine for failure to achieve the benchmark. WP is unable to predict the outcome of this matter or estimate any possible loss or range of loss.

In December 2009, WP filed a motion to reopen the evidentiary record to submit an alternative smart meter plan proposing, among other things, a less-rapid deployment of smart meters.

In light of the significant expenditures that would be associated with its smart meter deployment plans and related infrastructure upgrades, as well as its evaluation of recent PPUC decisions approving less-rapid deployment proposals by other utilities, WP re-evaluated its Act 129 compliance strategy, including both its plans with respect to smart meter deployment and certain smart meter dependent aspects of the EE&C Plan. In October 2010, WP and Pennsylvania's OCA filed a Joint Petition for Settlement addressing WP's smart meter implementation plan with the PPUC. Under the terms of the proposed settlement, WP proposed to decelerate its previously contemplated smart meter deployment schedule and to target the installation of approximately 25,000 smart meters in support of its EE&C Plan, based on customer requests, by mid-2012. The proposed settlement also contemplates that WP take advantage of the 30-month grace period authorized by the PPUC to continue WP's efforts to re-evaluate full-scale smart meter deployment plans. WP currently anticipates filing its plan for full-scale deployment of smart meters in June 2012. Under the terms of the proposed settlement, WP would be permitted to recover certain previously incurred and anticipated smart-meter related expenditures through a levelized customer surcharge, with certain expenditures amortized over a ten-year period. Additionally, WP would be permitted to seek recovery of certain other costs as part of its revised SMIP that it currently intends to file in June 2012, or in a future base distribution rate case.
Following additional proceedings, on March 9, 2011, WP submitted an Amended Joint Petition for Settlement which restates the Joint Petition for Settlement filed in October 2010, adds the PPUC's Office of Trial Staff as a signatory party, and confirms the support or non-opposition of all parties to the settlement. One party retained the ability to challenge the recovery of amounts spent on WP's original smart meter implementation plan. A Joint Stipulation with the OSBA was also filed on March 9, 2011. The PPUC approved the Amended Joint Petition for Full Settlement by order entered June 30, 2011.

By Tentative Order entered in September 2009, the PPUC provided for an additional 30-day comment period on whether the 1998 Restructuring Settlement, which addressed how Met-Ed and Penelec were going to implement direct access to a competitive market for the generation of electricity, allows Met-Ed and Penelec to apply over-collection of NUG costs for select and isolated months to reduce non-NUG stranded costs when a cumulative NUG stranded cost balance exists. In response to the Tentative Order, various parties filed comments objecting to the accounting method utilized by Met-Ed and Penelec. On January 30, 2012, the Commission entered a final order approving Met-Ed's and Penelec's accounting methodology whereby NUG over-collection revenue may be used to reduce non-NUG stranded costs, even if a cumulative NUG stranded cost balance exists.

In the PPUC Order approving the FirstEnergy and Allegheny merger, the PPUC announced that a separate statewide investigation into Pennsylvania's retail electricity market will be conducted with the goal of making recommendations for improvements to ensure that a properly functioning and workable competitive retail electricity market exists in the state. On April 29, 2011, the PPUC entered an Order initiating the investigation and requesting comments from interested parties on eleven directed questions concerning retail markets in Pennsylvania. Met-Ed, Penelec, Penn Power and WP submitted joint comments on June 3, 2011. FES also submitted comments on June 3, 2011. On June 8, 2011, the PPUC conducted an en banc hearing on these issues at which both the Pennsylvania Companies and FES participated and offered testimony. A technical conference was held on August 10, 2011, and a second en banc was held on November 10, 2011, to discuss intermediate steps that can be taken to promote the development of a competitive market. Teleconferences are scheduled through March 2012, with another en banc hearing to be held on March 21, 2012, to explore the future of default service in Pennsylvania following the expiration of the upcoming default service plans on May 31, 2015. Following the issuance of a Tentative Order and comments filed by numerous parties, the Commission entered a final order on December 16, 2011, providing recommendations for components to be included in upcoming default service plans. An intermediate work plan was also presented on December 16, 2011, by Tentative Order, on which initial comments were submitted by Met-Ed, Penelec, Penn and WP on January 17, 2012. FES also submitted comments. Reply comments were submitted on February 1, 2012. It is expected that a final order implementing the intermediate work plan and a long range plan will be presented by the PPUC, both in March 2012.

The PPUC issued a Proposed Rulemaking Order on August 25, 2011, which proposed a number of substantial modifications to the current Code of Conduct regulations that were promulgated to provide competitive safeguards to the competitive retail electric market in Pennsylvania. The proposed changes include, but are not limited to: an EGS may not have the same or substantially similar name as the EDC or its corporate parent; EDCs and EGSs would not be permitted to share office space and would need to occupy different buildings; EDCs and affiliated EGSs could not share employees or services, except certain corporate support, emergency, or tariff services (the definition of "corporate support services" excludes items such as information systems, electronic data interchange, strategic management and planning, regulatory services, legal services, or commodities that have been included in regulated rates at less than market value); and an EGS must enter into a trademark agreement with the EDC before using its trademark or service mark. The Proposed Rulemaking Order, which was published on February 11, 2012, calls for comments to be submitted by March 27, 2012. If implemented these rules could require a significant change in the way FES, Met-Ed, Penelec, Penn and WP do business in Pennsylvania, and could possibly have an adverse impact on their results of operations and financial condition.

In November 2011, Met-Ed, Penelec, Penn and WP filed a Joint Petition for Approval of their Default Service Plan for the period June 1, 2013 through May 31, 2015. The Pennsylvania Companies' direct case was submitted in its entirety on December 20, 2011. Evidentiary hearings are scheduled for April 11-13, 2012, and a final order must be entered by the PPUC by August 17, 2012.

WEST VIRGINIA
In 2009, the West Virginia Legislature enacted the AREPA, which generally requires that a specified minimum percentage of electricity sold to retail customers in West Virginia by electric utilities each year be derived from alternative and renewable energy resources according to a predetermined schedule of increasing percentage targets, including 10% by 2015, 15% by 2020, and 25% by 2025. In November 2010, the WVPSC issued RPS Rules, which became effective on January 4, 2011. Under the RPS Rules, on or before January 1, 2011, each electric utility subject to the provisions of this rule was required to prepare an alternative and renewable energy portfolio standard compliance plan and file an application with the WVPSC seeking approval of such plan. MP and PE filed their combined compliance plan in December 2010. A hearing was held at the WVPSC on June 13, 2011. An order was issued by the WVPSC in September 2011, which conditionally approved MP's and PE's compliance plan, contingent on the outcome of the resource credits case discussed below.

Additionally, in January 2011, MP and PE filed an application with the WVPSC seeking to certify three facilities as Qualified Energy Resource Facilities. The application was approved and the three facilities are capable of generating renewable credits which will assist the companies in meeting their combined requirements under the AREPA. An annual update filing is due on March 31, 2012. Further, in February 2011, MP and PE filed a petition with the WVPSC seeking an Order declaring that MP is entitled to all alternative and renewable energy resource credits associated with the electric energy, or energy and capacity, that MP is required to purchase pursuant to electric energy purchase agreements between MP and three non-utility electric generating facilities in West Virginia. The City of New Martinsville and Morgantown Energy Associates, each the owner of one of the contracted resources, has participated in the case in opposition to the Petition. A hearing was held at the WVPSC on August 25 and 26, 2011. On November 22, 2011, the WVPSC issued an order granting ownership of all RECs produced by the facilities to MP. On December 22, 2011, the WVPSC order was appealed, and the order was stayed pending the outcome of the appeal. MP's brief was filed on February 13, 2012. Should MP be unsuccessful in the appeal, it will have to procure the requisite RECs to comply with AREPA from other sources. MP expects to recover such costs from customers.

In September 2011, MP and PE filed with the WVPSC to recover costs associated with fuel and purchased power (the ENEC) in the amount of $32 million which represents an approximate 3% overall increase in such costs over the past two years, primarily attributable to rising coal prices. The requested increase was partially offset by $2.5 million of synergy savings directly resulting from the merger of FirstEnergy and AE, which closed in February 2011. Under a cost recovery clause established by the WVPSC in 2007, MP and PE customer bills are adjusted periodically to reflect upward or downward changes in the cost of fuel and purchased power. The utilities' most recent request to recover costs for fuel and purchased power was in September 2009. MP and PE entered into a Settlement Agreement related to this matter. The WVPSC issued an order on December 30, 2011, approving the settlement agreement. The approved settlement resulted in an increase of $19.6 million, instead of the requested $32 million, with additional costs to be recovered over time with a carrying charge.

FERC MATTERS

PJM Transmission Rate

In April 2007, FERC issued Opinion 494 finding that the PJM transmission owners' existing “license plate” or zonal rate design was just and reasonable and ordered that the current license plate rates for existing transmission facilities be retained. On the issue of rates for new transmission facilities, FERC directed that costs for new transmission facilities that are rated at 500 kV or higher are to be collected from all transmission zones throughout the PJM footprint by means of a postage-stamp rate based on the amount of load served in a transmission zone. Costs for new transmission facilities that are rated at less than 500 kV, however, are to be allocated on a load flow methodology, which is generally referred to as a “beneficiary pays” approach to allocating the cost of high voltage transmission facilities.

FERC's Opinion 494 order was appealed to the U.S. Court of Appeals for the Seventh Circuit, which issued a decision in August 2009. The court affirmed FERC's ratemaking treatment for existing transmission facilities, but found that FERC had not supported its decision to allocate costs for new 500 kV and higher voltage facilities on a load ratio share basis and, based on this finding, remanded the rate design issue to FERC.

In an order dated January 21, 2010, FERC set the matter for a “paper hearing” and requested parties to submit written comments pursuant to the schedule described in the order. FERC identified nine separate issues for comments and directed PJM to file the first round of comments on February 22, 2010, with other parties submitting responsive comments and then reply comments on later dates. PJM filed certain studies with FERC on April 13, 2010, in response to the FERC order. PJM's filing demonstrated that allocation of the cost of high voltage transmission facilities on a beneficiary pays basis results in certain load serving entities in PJM bearing the majority of the costs. Numerous parties filed responsive comments or studies on May 28, 2010 and reply comments on June 28, 2010. FirstEnergy and a number of other utilities, industrial customers and state commissions supported the use of the beneficiary pays approach for cost allocation for high voltage transmission facilities. Other utilities and state commissions supported continued socialization of these costs on a load ratio share basis. This matter is awaiting action by FERC. FirstEnergy cannot predict the outcome of this matter or estimate the possible loss or range of loss.

RTO Realignment

On June 1, 2011, ATSI and the ATSI zone entered into PJM. The move was performed as planned with no known operational or reliability issues for ATSI or for the wholesale transmission customers in the ATSI zone.

On February 1, 2011, ATSI in conjunction with PJM filed its proposal with FERC for moving its transmission rate into PJM's tariffs. On April 1, 2011, the MISO TOs (including ATSI) filed proposed tariff language that describes the mechanics of collecting and administering MTEP costs from ATSI-zone ratepayers. From March 20, 2011 through April 1, 2011, FirstEnergy, PJM and the MISO submitted numerous filings for the purpose of effecting movement of the ATSI zone to PJM on June 1, 2011. These filings include amendments to the MISO's tariffs (to remove the ATSI zone), submission of load and generation interconnection agreements to reflect the move into PJM, and submission of changes to PJM's tariffs to support the move into PJM.

On May 31, 2011, FERC issued orders that address the proposed ATSI transmission rate, and certain parts of the MISO tariffs that reflect the mechanics of transmission cost allocation and collection. In its May 31, 2011 orders, FERC approved ATSI's proposal to move the ATSI formula rate into the PJM tariff without significant change. Speaking to ATSI's proposed treatment of the MISO's exit fees and charges for transmission costs that were allocated to the ATSI zone, FERC required ATSI to present a cost-benefit study that demonstrates that the benefits of the move for transmission customers exceed the costs of any such move, which FERC had not previously required. Accordingly, FERC ruled that these costs must be removed from ATSI's proposed transmission rates until such time as ATSI files and FERC approves the cost-benefit study. On June 30, 2011, ATSI submitted the compliance filing that removed the MISO exit fees and transmission cost allocation charges from ATSI's proposed transmission rates. Also on June 30, 2011, ATSI requested rehearing of FERC's decision to require a cost-benefit analysis as part of FERC's evaluation of ATSI's proposed transmission rates. Finally, and also on June 30, 2011, the MISO and the MISO TOs filed a competing compliance filing - one that would require ATSI to pay certain charges related to construction and operation of transmission projects within the MISO even though FERC ruled that ATSI cannot pass these costs on to ATSI's customers. ATSI on the one hand, and the MISO and MISO TOs on the other, have submitted subsequent filings - each of which is intended to refute the other's claims. ATSI's compliance filing and request for rehearing, as well as the pleadings that reflect the dispute between ATSI and the MISO/MISO TOs, are currently pending before FERC.

From late April 2011 through June 2011, FERC issued other orders that address ATSI's move into PJM. Also, ATSI and the MISO were able to negotiate an agreement of ATSI's responsibility for certain charges associated with long term firm transmission rights that, according to the MISO, were payable by the ATSI zone upon its departure from the MISO. ATSI did not and does not agree that these costs should be charged to ATSI but, in order to settle the case and all claims associated with the case, ATSI agreed to a one-time payment of $1.8 million to the MISO. This settlement agreement has been submitted for FERC's review and approval. The final outcome of those proceedings that address the remaining open issues related to ATSI's move into PJM and their impact, if any, on FirstEnergy cannot be predicted at this time.

MISO Multi-Value Project Rule Proposal

In July 2010, MISO and certain MISO transmission owners jointly filed with FERC their proposed cost allocation methodology for certain new transmission projects. The new transmission projects--described as MVPs - are a class of transmission projects that are approved via the MTEP. The filing parties proposed to allocate the costs of MVPs by means of a usage-based charge that will be applied to all loads within the MISO footprint, and to energy transactions that call for power to be “wheeled through” the MISO as well as to energy transactions that “source” in the MISO but “sink” outside of MISO. The filing parties expect that the MVP proposal will fund the costs of large transmission projects designed to bring wind generation from the upper Midwest to load centers in the east. The filing parties requested an effective date for the proposal of July 16, 2011. On August 19, 2010, MISO's Board approved the first MVP project -- the “Michigan Thumb Project.” Under MISO's proposal, the costs of MVP projects approved by MISO's Board prior to the June 1, 2011 effective date of FirstEnergy's integration into PJM would continue to be allocated to FirstEnergy. MISO estimated that approximately $15 million in annual revenue requirements would be allocated to the ATSI zone associated with the Michigan Thumb Project upon its completion.

In September 2010, FirstEnergy filed a protest to the MVP proposal arguing that MISO's proposal to allocate costs of MVPs projects across the entire MISO footprint does not align with the established rule that cost allocation is to be based on cost causation (the “beneficiary pays” approach). FirstEnergy also argued that, in light of progress that had been made to date in the ATSI integration into PJM, it would be unjust and unreasonable to allocate any MVP costs to the ATSI zone, or to ATSI. Numerous other parties filed pleadings on MISO's MVP proposal.

In December 2010, FERC issued an order approving the MVP proposal without significant change. Despite being presented with the issue by FirstEnergy and the MISO, the FERC did not address clearly the question of whether the MVP costs would be payable by ATSI or load in the ATSI zone. FERC stated that the MISO's tariffs obligate ATSI to pay all charges that attached prior to ATSI's exit but ruled that the question of the amount of costs that are to be allocated to ATSI or to load in the ATSI zone were beyond the scope of FERC's order and would be addressed in future proceedings.

On January 18, 2011, FirstEnergy requested rehearing of FERC's order. In its rehearing request, FirstEnergy argued that because the MVP rate is usage-based, costs could not be applied to ATSI, which is a stand-alone transmission company that does not use the transmission system. FirstEnergy also renewed its arguments regarding cost causation and the impropriety of allocating costs to the ATSI zone or to ATSI. On October 21, 2011, FERC issued its order on rehearing, but that order did not address FirstEnergy's argument directly. FERC ruled instead that if ATSI was subject to MVP charges then ATSI owed these charges upon exit of the MISO. On October 31, 2011, FESC filed a Petition of Review for the FERC's December 2010 order and October 21, 2011 order on rehearing of that order with the U.S. Court of Appeals for the D.C. Circuit. Other parties also filed appeals of those orders and, in November, 2011, the cases were consolidated for briefing and disposition in the U.S. Court of Appeals for the Seventh Circuit. On January 27, 2012, the court ordered the FERC to file a proposed briefing format and schedule on or before March 20, 2012.

On August 3, 2011, FirstEnergy filed a complaint with FERC based on the FERC's December 2010 order. In the complaint, FirstEnergy argued that ATSI perfected the legal and financial requirements necessary to exit MISO before any MVP responsibilities could attach and asked FERC to rule that MISO cannot charge ATSI for MVP costs. On September 2, 2011, MISO, its TOs and other parties, filed responsive pleadings. On September 19, 2011, ATSI filed an answer. On December 29, 2011, the MISO and the MISO TOs filed a new “Schedule 39” to the MISO's tariff. Schedule 39 purports to establish a process whereby the MISO would bill TOs for MVP costs that, according to the MISO, attached to the utility prior to such TOs withdrawal from the MISO. On January 19, 2012, FirstEnergy filed a protest to the MISO's new Schedule 39 tariff.

On February 27, 2012, FERC issued an order (February 2012 Order) dismissing ATSI's August 3, 2011 complaint. In the February 2012 Order, FERC accepted the MISO's Schedule 39 tariff, subject to hearings and potential refund of MVP charges to ATSI. The basis for any subsequent hearing is whether the Schedule 39 tariff was in effect at the time that ATSI exited the MISO. FirstEnergy is evaluating the February 2012 Order and will determine the next steps.

FirstEnergy cannot predict the outcome of these proceedings or estimate the possible loss or range of loss.

FirstEnergy Companies' PJM Underfunding FTR Contract Complaint

On December 28, 2011, FES and AE Supply filed a complaint with FERC against PJM challenging the ongoing underfunding of FTR contracts, which exist to hedge against transmission congestion in the day-ahead markets. The underfunding is a result of PJM's practice of using the funds that are intended to pay the holders of FTR contracts to pay instead for congestion costs that occur in the real time markets. Underfunding of the FTR contracts resulted in losses of approximately $35 million to FES and AE Supply in the 2010-2011 Delivery Year. To date, losses for the 2011-2012 Delivery Year are estimated to be approximately $6 million.

On January 13, 2012, PJM filed comments that describe changes to the PJM tariff that, if adopted, should remedy the underfunding issue. Many parties also filed comments supporting FES' and AE Supply's position. Other parties, generally representatives of end-use customers who will have to pay the charges, filed in opposition to the complaint. The matter is currently pending before FERC. FirstEnergy cannot predict the outcome of this matter or estimate the possible loss or range of loss.

California Claims Matters

In October 2006, several California governmental and utility parties presented AE Supply with a settlement proposal to resolve alleged overcharges for power sales by AE Supply to the California Energy Resource Scheduling division of the CDWR during 2001. The settlement proposal claims that CDWR is owed approximately $190 million for these alleged overcharges. This proposal was made in the context of mediation efforts by FERC and the United States Court of Appeals for the Ninth Circuit in pending proceedings to resolve all outstanding refund and other claims, including claims of alleged price manipulation in the California energy markets during 2000 and 2001. The Ninth Circuit has since remanded one of those proceedings to FERC, which arises out of claims previously filed with FERC by the California Attorney General on behalf of certain California parties against various sellers in the California wholesale power market, including AE Supply (the Lockyer case). AE Supply and several other sellers filed motions to dismiss the Lockyer case. In March 2010, the judge assigned to the case entered an opinion that granted the motions to dismiss filed by AE Supply and other sellers and dismissed the claims of the California Parties. On May 4, 2011, FERC affirmed the judge's ruling. On June 3, 2011, the California parties requested rehearing of the May 4, 2011 order. The request for rehearing remains pending.

In June 2009, the California Attorney General, on behalf of certain California parties, filed a second complaint with FERC against various sellers, including AE Supply (the Brown case), again seeking refunds for trades in the California energy markets during 2000 and 2001. The above-noted trades with CDWR are the basis for including AE Supply in this new complaint. AE Supply filed a motion to dismiss the Brown complaint that was granted by FERC on May 24, 2011. On June 23, 2011, the California Attorney General requested rehearing of the May 24, 2011 order. That request for rehearing also remains pending. FirstEnergy cannot predict the outcome of either of the above matters or estimate the possible loss or range of loss.

PATH Transmission Project

The PATH Project is comprised of a 765 kV transmission line that was proposed to extend from West Virginia through Virginia and into Maryland, modifications to an existing substation in Putnam County, West Virginia, and the construction of new substations in Hardy County, West Virginia and Frederick County, Maryland.

PJM initially authorized construction of the PATH Project in June 2007. In December 2010, PJM advised that its 2011 Load Forecast Report included load projections that are different from previous forecasts and that may have an impact on the proposed in-service date for the PATH Project. As part of its 2011 RTEP, and in response to a January 19, 2011, directive by a Virginia Hearing Examiner, PJM conducted a series of analyses using the most current economic forecasts and demand response commitments, as well as potential new generation resources. Preliminary analysis revealed the expected reliability violations that necessitated the PATH Project had moved several years into the future. Based on those results, PJM announced on February 28, 2011, that its Board of Managers had decided to hold the PATH Project in abeyance in its 2011 RTEP and directed FirstEnergy and AEP, as the sponsoring transmission owners, to suspend current development efforts on the project, subject to those activities necessary to maintain the project in its current state, while PJM conducts more rigorous analysis of the need for the project as part of its continuing RTEP process. PJM stated that its action did not constitute a directive to FirstEnergy and AEP to cancel or abandon the PATH Project. PJM further stated that it will complete a more rigorous analysis of the PATH Project and other transmission requirements and its Board will review this comprehensive analysis as part of its consideration of the 2011 RTEP. On February 28, 2011, affiliates of FirstEnergy and AEP filed motions or notices to withdraw applications for authorization to construct the project that were pending before state commissions in West Virginia, Virginia and Maryland. Withdrawal was deemed effective upon filing the notice with the MDPSC. The WVPSC and VSCC have granted the motions to withdraw.

PATH submitted a filing to FERC to implement a formula rate tariff effective March 1, 2008. In a November 19, 2010 order addressing various matters relating to the formula rate, FERC set the project's base ROE for hearing and reaffirmed its prior authorization of a return on CWIP, recovery of start-up costs and recovery of abandonment costs. In the order, FERC also granted a 1.5% ROE incentive adder and a 0.5% ROE adder for RTO participation. These adders will be applied to the base ROE determined as a result of the hearing. The PATH Companies, Joint Intervenors, Joint Consumer Advocates and FERC staff have agreed to a four year moratorium. A settlement was reached, which reflects a base ROE of 10.4% (plus authorized adders) effective January 1, 2011. Accordingly, the revised ROE was reflected in a revised Projected Transmission Revenue Requirement for 2011 with true-up occurring in 2013. The FirstEnergy portion of the refund for March 1, 2008, through December 31, 2010, is approximately $2 million (inclusive of interest). The refund amount was computed using a base ROE of 10.8% plus authorized adders. On October 7, 2011, PATH and six intervenors submitted to FERC an unopposed settlement agreement. Contemporaneous with this submission, PATH and the six intervenors filed with the Chief ALJ of FERC a joint motion for interim approval and authorization to implement the refund on an interim basis pending issuance of a FERC order acting on the settlement agreement. On October 12, 2011, the motion for interim approval and authorization to implement the refund was granted by the Chief ALJ. On February 16, 2012, FERC approved the settlement agreement and dismissed as moot, in light of its approval of the settlement, PATH's pending request for rehearing of the November 19, 2010 order.
Yards Creek
The Yards Creek Pumped Storage Project is a 400 MW hydroelectric project located in Warren County, New Jersey. JCP&L owns an undivided 50% interest in the project, and operates the project. PSEG Fossil, LLC, a subsidiary of Public Service Enterprise Group, owns the remaining interest in the plant. The project was constructed in the early 1960s, and became operational in 1965. Authorization to operate the project is by a license issued by the FERC. The existing license expires on February 28, 2013.

In February 2011, JCP&L and PSEG filed a joint application with FERC to renew the license for an additional forty years. The companies are pursuing relicensure through FERC's ILP. Under the ILP, FERC will assess the license applications, issue draft and final Environmental Assessments/Environmental Impact Studies (as required by NEPA), and provide opportunities for intervention and protests by affected third parties. FERC may hold hearings during the two-year ILP licensure period. FirstEnergy expects FERC to issue the new license within the remaining portion of the two-year ILP period. To the extent, however, that the license proceedings extend beyond the February 28, 2013 expiration date for the current license, the current license will be extended yearly as necessary to permit FERC to issue the new license.
Seneca