Costs and Estimated Earnings on Uncompleted Contracts
6 Months Ended
Jun. 30, 2012
Contractors [Abstract]  
Costs and Estimated Earnings on Uncompleted Contracts
 
5.           Costs and Estimated Earnings on Uncompleted Contracts
 
Costs and estimated earnings on uncompleted contracts consist of the following at June 30, 2012 and December 31, 2011:
 
   
2012
   
2011
 
Costs incurred on uncompleted contracts
  $ 10,384     $ 424,477  
Estimated earnings
    17,484       41  
      27,868       424,518  
Less:  billings to date
    (20,793 )     (358,064 )
                 
    $ 7,075     $ 66,454  
 
The above amounts are included in the accompanying balance sheets under the following captions at June 30, 2012 and December 31, 2011.
 
   
2012
   
2011
 
Costs and estimated earnings in excess of billings on uncompleted contracts
  $ 8,789     $ 66,454  
Billings in excess of cost and estimated earnings on uncompleted contracts
    (1,714 )     -  
    $ 7,075     $ 66,454  
   
Although management believes it has established adequate procedures for estimating costs to complete on open contracts, it is at least reasonably possible that additional significant costs could occur on contracts prior to completion. The Company periodically evaluates and revises its estimates and makes adjustments when they are considered necessary.