Restructuring and Other Costs [Text Block] Restructuring Costs
During the six months ended June 30, 2019, we recorded net pre-tax restructuring costs totaling $178 million for new and ongoing restructuring actions. We recorded charges in the segments as follows:
(dollars in millions)
 
Otis
$
40

Carrier
63

Pratt & Whitney
17

Collins Aerospace Systems
56

Eliminations and other
2

Total
$
178


Restructuring charges incurred during the six months ended June 30, 2019 primarily relate to actions initiated during 2019 and 2018, and were recorded as follows:
(dollars in millions)
 
Cost of sales
$
82

Selling, general and administrative
96

Total
$
178


2019 Actions. During the six months ended June 30, 2019, we recorded net pre-tax restructuring costs of $115 million, comprised of $43 million in cost of sales and $72 million in selling, general and administrative expenses. The 2019 actions relate to ongoing cost reduction efforts, including workforce reductions and the consolidation of field and manufacturing operations.
We are targeting to complete the majority of the remaining workforce and facility related cost reduction actions during 2019 and 2020. No specific plans for other significant actions have been finalized at this time. The following table summarizes the accrual balance and utilization for the 2019 restructuring actions for the quarter and six months ended June 30, 2019:
(dollars in millions)
Severance
 
Facility Exit, Lease Termination and Other Costs
 
Total
Quarter Ended June 30, 2019
 
 
 
 
 
Restructuring accruals at March 31, 2019
$
53

 
$
15

 
$
68

Net pre-tax restructuring costs
42

 

 
42

Utilization, foreign exchange and other costs
(38
)
 
(4
)
 
(42
)
Balance at June 30, 2019
$
57

 
$
11

 
$
68

 
 
 
 
 
 
Six Months Ended June 30, 2019
 
 
 
 
 
Net pre-tax restructuring costs
$
110

 
$
5

 
$
115

Utilization, foreign exchange and other costs
(53
)
 
6

 
(47
)
Balance at June 30, 2019
$
57

 
$
11

 
$
68


The following table summarizes expected, incurred and remaining costs for the 2019 restructuring actions by segment:
(dollars in millions)
Expected
Costs
 
Costs Incurred Quarter Ended
March 31, 2019
 
Costs Incurred Quarter Ended
June 30, 2019
 
Remaining Costs at
June 30, 2019
Otis
$
48

 
$
(19
)
 
$
(14
)
 
$
15

Carrier
77

 
(25
)
 
(24
)
 
28

Pratt & Whitney
17

 
(14
)
 
(3
)
 

Collins Aerospace Systems
44

 
(14
)
 

 
30

Eliminations and other
2

 
(1
)
 
(1
)
 

Total
$
188

 
$
(73
)
 
$
(42
)
 
$
73


2018 Actions. During the six months ended June 30, 2019, we recorded net pre-tax restructuring costs totaling $39 million for restructuring actions initiated in 2018, including $20 million in cost of sales and $19 million in selling, general and administrative expenses. The 2018 actions relate to ongoing cost reduction efforts, including workforce reductions, consolidation of field and manufacturing operations, and costs to exit legacy programs. The following table summarizes the accrual balances and utilization for the 2018 restructuring actions for the quarter and six months ended June 30, 2019:
(dollars in millions)
Severance
 
Facility Exit,
Lease
Termination and
Other Costs
 
Total
Quarter Ended June 30, 2019
 
 
 
 
 
Restructuring accruals at March 31, 2019
$
62

 
$
9

 
$
71

Net pre-tax restructuring costs
14

 
2

 
16

Utilization, foreign exchange and other costs
(28
)
 
(2
)
 
(30
)
Balance at June 30, 2019
$
48

 
$
9

 
$
57

 
 
 
 
 
 
Six Months Ended June 30, 2019
 
 
 
 
 
Restructuring accruals at December 31, 2018
$
115

 
$
23

 
$
138

Net pre-tax restructuring costs
35

 
4

 
39

Utilization, foreign exchange and other costs
(102
)
 
(18
)
 
(120
)
Balance at June 30, 2019
$
48

 
$
9

 
$
57


The following table summarizes expected, incurred and remaining costs for the 2018 restructuring actions by segment:
(dollars in millions)
Expected
Costs
 
Costs Incurred in 2018
 
Costs Incurred Quarter Ended
March 31, 2019
 
Costs Incurred Quarter Ended
June 30, 2019
 
Remaining Costs at
June 30, 2019
Otis
$
58

 
$
(48
)
 
$
(5
)
 
$
(1
)
 
$
4

Carrier
85

 
(64
)
 
(7
)
 
(6
)
 
8

Pratt & Whitney
3

 
(3
)
 

 

 

Collins Aerospace Systems
115

 
(87
)
 
(11
)
 
(9
)
 
8

Eliminations and other
5

 
(5
)
 

 

 

Total
$
266

 
$
(207
)
 
$
(23
)
 
$
(16
)
 
$
20


2017 and Prior Actions. During the six months ended June 30, 2019, we recorded net pre-tax restructuring costs totaling $24 million for restructuring actions initiated in 2017 and prior. As of June 30, 2019, we have approximately $74 million of accrual balances remaining related to 2017 and prior actions.