-----BEGIN PRIVACY-ENHANCED MESSAGE----- Proc-Type: 2001,MIC-CLEAR Originator-Name: webmaster@www.sec.gov Originator-Key-Asymmetric: MFgwCgYEVQgBAQICAf8DSgAwRwJAW2sNKK9AVtBzYZmr6aGjlWyK3XmZv3dTINen TWSM7vrzLADbmYQaionwg5sDW3P6oaM5D3tdezXMm7z1T+B+twIDAQAB MIC-Info: RSA-MD5,RSA, Tjj4PxwDSTcll2WjdwWV2ZRhxWSX2mrT/SF8QVmbIBgS7ml1xymBvvL5mDISnGPP +DPIySyJqT/uCRidTtoU7w== 0000950142-08-000442.txt : 20080219 0000950142-08-000442.hdr.sgml : 20080218 20080219111443 ACCESSION NUMBER: 0000950142-08-000442 CONFORMED SUBMISSION TYPE: 6-K PUBLIC DOCUMENT COUNT: 2 CONFORMED PERIOD OF REPORT: 20080213 FILED AS OF DATE: 20080219 DATE AS OF CHANGE: 20080219 FILER: COMPANY DATA: COMPANY CONFORMED NAME: CANADIAN NATURAL RESOURCES LTD CENTRAL INDEX KEY: 0001017413 STANDARD INDUSTRIAL CLASSIFICATION: CRUDE PETROLEUM & NATURAL GAS [1311] IRS NUMBER: 000000000 STATE OF INCORPORATION: A0 FISCAL YEAR END: 1231 FILING VALUES: FORM TYPE: 6-K SEC ACT: 1934 Act SEC FILE NUMBER: 333-12138 FILM NUMBER: 08625403 BUSINESS ADDRESS: STREET 1: 2500, 855-2 STREET SW CITY: CALGARY ALBERTA CANADA STATE: A0 ZIP: T2P 4J8 BUSINESS PHONE: 403-517-6700 MAIL ADDRESS: STREET 1: 2500, 855-2 STREET SW CITY: CALGARY ALBERTA CANADA STATE: A0 ZIP: T2P 4J8 6-K 1 form6k_021308.txt FORM 6-K ================================================================================ UNITED STATES SECURITIES AND EXCHANGE COMMISSION Washington, D.C. 20549 FORM 6-K REPORT OF FOREIGN PRIVATE ISSUER PURSUANT TO SECTION 13A-16 OR 15D-16 OF THE SECURITIES EXCHANGE ACT OF 1934 Press Releases February, 2008 Commission File Number: 1-8795 CANADIAN NATURAL RESOURCES LIMITED ------------------------------------------------------ (Exact name of registrant as specified in its charter) 2500, 855 - 2ND STREET S.W., CALGARY, ALBERTA, CANADA T2P 4J8 ------------------------------------------------------------- (Address of principal executive offices) Indicate by check mark whether the registrant files or will file annual reports under cover Form 20-F or Form 40-F. Form 20-F [_] Form 40-F [X] Indicate by check mark if the registrant is submitting the Form 6-K in paper as permitted by Regulation S-T Rule 101(b)(1). ____ Note: Regulation S-T Rule 101(b)(1) only permits the submission in paper of a Form 6-K if submitted solely to provide an attached annual report to security holders. Indicate by check mark if the registrant is submitting the Form 6-K in paper as permitted by Regulation S-T Rule 101(b)(7): ____ Note: Regulation S-T Rule 101(b)(7) only permits the submission in paper of a Form 6-K if submitted to furnish a report or other document that the registrant foreign private issuer must furnish and make public under the laws of the jurisdiction in which the registrant is incorporated, domiciled or legally organized (the registrant's "home country"), or under the rules of the home country exchange on which the registrant's securities are traded, as long as the report or other document is not a press release, is not required to be and has not been distributed to the registrant's security holders, and, if discussing a material event, has already been the subject of a Form 6-K submission or other Commission filing on EDGAR. Indicate by check mark whether the registrant by furnishing the information contained in this Form is also thereby furnishing the information to the Commission pursuant to Rule 12g3-2(b) under the Securities Exchange Act of 1934. Yes [_] No [X] If "Yes" is marked, indicate below the file number assigned to the registrant in connection with Rule 12g3-2(b): 82-______ ================================================================================ EXHIBIT NUMBER DESCRIPTION - -------------- ----------- 99.1 Canadian Natural Resources Limited Announces Fourth Quarter 2997 Update on the Progress of the Horizon Oil Sands Project February 12, 2008 SIGNATURE Pursuant to the requirements of the Securities Exchange Act of 1934, the registrant has duly caused this report to be signed on its behalf by the undersigned, thereunto duly authorized. CANADIAN NATURAL RESOURCES LIMITED (Registrant) Date: February 13, 2008 By: /s/ Bruce E. McGrath ---------------------------- Bruce E. McGrath Corporate Secretary EX-99 2 ex99-1form6k_021308.txt EXHIBIT 99.1 EXHIBIT 99.1 ------------ - ------------------------------------------------------------------------------- [GRAPHICS OMITTED - LOGO, PHOTOGRAPHS] - --------------- News Release ------------- --------------- ------------ Discipline Opportunity Strategy - ------------------------------------------------------------------------------- CANADIAN NATURAL RESOURCES LIMITED ANNOUNCES FOURTH QUARTER 2007 UPDATE ON THE PROGRESS OF THE HORIZON OIL SANDS PROJECT CALGARY, ALBERTA - FEBRUARY 12, 2008 - FOR IMMEDIATE RELEASE Canadian Natural Resources Limited ("Canadian Natural") is pleased to provide its regular quarterly update on the Horizon Oil Sands Project ("Horizon Project"). Commenting on fourth quarter progress on the Horizon Oil Sands Project, Real Doucet, Sr. Vice President, Oil Sands stated, "We achieved 90% completion of the Horizon Project by year-end 2007, a major accomplishment, which remains on track for first oil in the third quarter of 2008. The remaining 10%, however, is in many ways the toughest as it is the most labour intensive portion of the Horizon Project. Unfortunately, mid to late January and early February saw a significant deterioration in labour productivity on the construction site as much colder than normal weather seriously curtailed activity. The weather also affected the commissioning schedule of certain plants; however, at present this is not expected to have any impact on our targeted completion of Phase 1." "As of December 31, 2007 our forecasted total costs of the Horizon Project were at 13.4% over our $6.8 billion Board of Directors authorization. We just completed a thorough review of the productivity that we have recently experienced at the Horizon Project construction site and have determined that should no improvements in productivity be achieved through the remainder of construction, then the cost estimate for Phase 1 of the Horizon Project would need to be increased to 28% above the original $6.8 billion Board authorization. If we can regain targeted labour efficiencies and productivity, this overage could be reduced to approximately 25% above the original $6.8 billion Board authorization. This range of outcomes will result in an on-stream cost of less than $80,000 bbl/d of capacity, including the benefits of the significant pre-build capital invested for Phase 2/3. In the fourth quarter of 2007, we reached many significant milestones including completion of the tailings pond, filling of the raw water pond and preparing two tanks to receive start-up diluent in January. We have experienced minor slippage in certain non-critical path plants where mechanical completion has moved from the end of the second quarter to early in the third quarter - having no expected impact however on targeted Project completion. Our critical path plants, Delayed Coker / Diluent Recovery Unit and Hydrotreater remain on track for first oil in the third quarter of this year. In parallel with completing major systems, we are getting ready for operations. Our rate of operations hiring and training has gained significant momentum with 100% of Mining, 89% of Bitumen Extraction, 80% of Upgrading and 76% of Utilities and Offsites staffing requirements hired to date. We have also now awarded all of the maintenance contracts, with these contractors immediately mobilizing to site in the last part of the fourth quarter of 2007. We remain focused on timely completion of Phase 1, while getting ready to operate the new facilities. Meanwhile, following Board authorization to proceed with Tranche 2 of our next expansion, we were immediately able to award a contract for an additional Ore Prep Plant to an existing contractor that is performing well. In addition, other long lead equipment (Coke Drums and Reactors) for Phase 2/3 will be delivered to site during the first quarter of 2008, as we look forward to successful construction and completion of future phases." Page 2 - ------------------------------------------------------------------------------- PROJECT STATUS SUMMARY
SEPTEMBER 30, 2007 DECEMBER 31, 2007 MARCH 31, 2008 ------------------ ----------------- -------------- Q4/07 Original Q1/08 Original ACTUAL ACTUAL FORECAST PLAN FORECAST PLAN ------ ------ -------- ---- -------- ---- Phase 1 - Work progress (cumulative) 84% 90% 90% 94% 95% 97% Phase 1 - Construction capital spending* 89% 99% 99% 92% 110% 97% (cumulative)
*Relative to overall Phase 1 project capital of $6.8 billion ACCOMPLISHED TO THE END OF THE FOURTH QUARTER OF 2007 DETAILED ENGINEERING o Overall detailed engineering 98.5% complete and substantially complete in most areas. PROCUREMENT o Overall procurement progress is 99% complete. o Awarded over $5.6 billion in purchase orders and contracts to date. o Only one significant contract remains to be awarded for Phase 1 - mechanical for Sulphur Blocking. o Commenced receipt and site assembly of Mine Operations Equipment (Shovels and Heavy Haul Trucks). o Operations and maintenance service and supply agreements have been awarded. MODULARIZATION o Delivered an additional 54 oversized loads to site for a total of 1,560 loads, representing approximately 94% of the total requirement. Remaining deliveries consist primarily of the balance of required Mine Operations Equipment (Shovels and Heavy Haul Trucks). CONSTRUCTION o Overall construction progress is 85% complete. o Mine overburden removal has moved 49.9 million bank cubic meters, which represents approximately 72% of the total to be moved and is 0.6 million bank cubic meters ahead of schedule. o Main Control Room Distributed Control Systems equipment powered and tested. o Commissioned 260kV Transmission line and turned over to operations. o Commissioned Raw Water Pumphouse and turned over to operations. o Completed reformer erection in Hydrogen Plant. o Completed installation and pre-commissioning of CPI Separator Building. o Completed the closure of Dyke 10 (external tailings pond) in Mining. o Completed erection of Crushing Plants and conveyors in Ore Preparation Area. o Completed Primary Separation Cells in Extraction. o Completed construction of Main Laboratory. MILESTONES FOR THE FIRST QUARTER OF 2008 o Mechanically Complete Extraction Plant. o Mechanically Complete Froth Treatment Plant. o Mechanically Complete Amine Plant. o Complete Auxiliary Boiler installation in Cogeneration. o Complete Piping in Heat Integration. Page 3 - ------------------------------------------------------------------------------- PLANT AND SYSTEM COMMISSIONING SCHEDULE COMPLETED o Permanent Potable Water Treatment o Permanent Sewage Treatment o Natural Gas Pipeline o Raw and Recycled Water Pipelines o River Water Intake and Pumphouse o Raw Water Pond and Pumphouse o Recycle Water Pond and Pumphouse o Electrical Distribution System Q1 2008 o Tanks 11 and 12 completed for early diluent fill o Main Piperack o Instrument and Utility Air System o Flare System Q2 2008 o Cogeneration o Cooling and Heating o Delayed Coker / Diluent Recovery Unit o Gas Treating and Sulphur Recovery o West Tank Farm (inter plant) o Sulphur Block Pipelines o Synthetic Crude Oil Pipeline Q3 2008 o Ore Preparation Plant o Extraction o Froth Treatment o Pipeline Corridors o Hydrogen Plant o Hydrotreater o East Tank Farm (product) A picture gallery providing visual updates on construction progress is available on the Company's website (HTTP://WWW.CNRL.COM/HORIZON/ABOUT_HORIZON/PHOTO_GALLERY.HTML). CONFERENCE CALL A conference call will be held at 7:30 a.m. Mountain Time, 9:30 a.m. Eastern Time on Tuesday, February 12, 2008. The North American conference call number is 1-866-540-8136 and the outside North American conference call number is 001-416-340-8010. Please call in about 10 minutes before the starting time in order to be patched into the call. The conference call will also be broadcast live on the internet and may be accessed through the Canadian Natural website at WWW.CNRL.COM. A taped rebroadcast will be available until 6:00 p.m. Mountain Time, Tuesday, February 19, 2008. To access the postview in North America, dial 1-800-408-3053. Those outside of North America, dial 001-416-695-5800. The passcode to use is 3252546. Page 4 - ------------------------------------------------------------------------------- WEBCAST This call is being webcast by Vcall and can be accessed on Canadian Natural's website at WWW.CNRL.COM/INVESTOR_INFO/CALENDAR.HTML. The webcast is also being distributed over PrecisionIR's Investor Distribution Network to both institutional and individual investors. Investors can listen to the call through www.vcall.com or by visiting any of the investor sites in PrecisionIR's Individual Investor Network. 2007 FOURTH QUARTER RESULTS The Company's results for the fourth quarter of 2007 will be released on February 28, 2008. A conference call will be held on that day at 9:00 a.m. Mountain Time, 11:00 a.m. Eastern Time. Canadian Natural is a senior oil and natural gas production company, with continuing operations in its core areas located in Western Canada, the U.K. portion of the North Sea and Offshore West Africa. Page 5 - ------------------------------------------------------------------------------- FORWARD-LOOKING STATEMENTS Certain statements in this document or documents incorporated herein by reference for Canadian Natural Resources Limited (the "Company") constitute "forward-looking statements" within the meaning of the United States Private Securities Litigation Reform Act of 1995. These forward-looking statements can generally be identified as such because of the context of the statements including words such as the Company "believes", "anticipates", "expects", "plans", "estimates", "targets", or words of a similar nature. The forward-looking statements are based on current expectations and are subject to known and unknown risks, uncertainties and other factors that may cause the actual results, performance or achievements of the Company, or industry results, to be materially different from any future results, performance or achievements expressed or implied by such forward-looking statements. Such factors include, among others: general economic and business conditions which will, among other things, impact demand for and market prices of the Company's products; foreign currency exchange rates; economic conditions in the countries and regions in which the Company conducts business; political uncertainty, including actions of or against terrorists, insurgent groups or other conflict including conflict between states; industry capacity; ability of the Company to implement its business strategy, including exploration and development activities; impact of competition; availability and cost of seismic, drilling and other equipment; ability of the Company to complete its capital programs; ability of the Company to transport its products to market; potential delays or changes in plans with respect to exploration or development projects or capital expenditures; ability of the Company to attract the necessary labour required to build its projects; operating hazards and other difficulties inherent in the exploration for and production and sale of crude oil and natural gas; availability and cost of financing; success of exploration and development activities; timing and success of integrating the business and operations of acquired companies; production levels; uncertainty of reserve estimates; actions by governmental authorities; government regulations and the expenditures required to comply with them (especially safety and environmental laws and regulations); asset retirement obligations; and other circumstances affecting revenues and expenses. Our domestic operations are subject to governmental risks that may impact our operations. Our domestic operations have been, and at times in the future may be affected by political developments and by federal, provincial and local laws and regulations such as restrictions on production, changes in taxes, royalties and other amounts payable to governments or governmental agencies, price or gathering rate controls and environmental protection regulations. The impact of any one factor on a particular forward-looking statement is not determinable with certainty as such factors are interdependent upon other factors, and the Company's course of action would depend upon its assessment of the future considering all information then available. Statements relating to "reserves" are deemed to be forward-looking statements as they involve the implied assessment based on certain estimates and assumptions that the reserves described can be profitably produced in the future. Readers are cautioned that the foregoing list of important factors is not exhaustive. Although the Company believes that the expectations conveyed by the forward-looking statements are reasonable based on information available to it on the date such forward-looking statements are made, no assurances can be given as to future results, levels of activity and achievements. All subsequent forward-looking statements, whether written or oral, attributable to the Company or persons acting on its behalf are expressly qualified in their entirety by these cautionary statements. Except as required by law, the Company assumes no obligation to update forward-looking statements should circumstances or Management's estimates or opinions change. For further information, please contact: CANADIAN NATURAL RESOURCES LIMITED 2500, 855 - 2nd Street S.W. Calgary, Alberta T2P 4J8 TELEPHONE: (403) 514-7777 ALLAN P. MARKIN FACSIMILE: (403) 514-7888 Chairman EMAIL: IR@CNRL.COM WEBSITE: WWW.CNRL.COM JOHN G. LANGILLE Vice-Chairman TRADING SYMBOL - CNQ STEVE W. LAUT Toronto Stock Exchange President & New York Stock Exchange Chief Operating Officer DOUGLAS A. PROLL Chief Financial Officer & Senior Vice-President, Finance COREY B. BIEBER Vice-President, Finance & Investor Relations
-----END PRIVACY-ENHANCED MESSAGE-----