Debt Including Capital Lease Obligations - Build-to-suit Lease (Details) (USD $)
1 Months Ended 16 Months Ended
Jun. 30, 2013
Dec. 31, 2012
Jun. 30, 2012
Jun. 30, 2012
U.S. Midwest
Salad production and warehousing facility
renewal_option
facility
Jun. 30, 2013
U.S. Midwest
Salad production and warehousing facility
Property, plant and equipment
Sep. 30, 2013
U.S. Midwest
Salad production and warehousing facility
Expected contribution in Q3 2013
Jun. 30, 2013
U.S. Midwest
Portion placed into service
Long-term debt and capital lease obligations
Jun. 30, 2013
U.S. Midwest
Construction in progress
Other liabilities
Capital Leased Assets [Line Items]                
Lease term       20 years        
Number of facilities that the leased facility will replace       3        
Number of lease extensions       2        
Lease extension term       5 years        
Capital leased asset         $ 39,000,000      
Capital lease obligations 14,250,000 [1] 755,000 827,000       14,000,000 25,000,000
Total build-to-suit lease construction costs           $ 40,000,000    
[1] Capital lease obligations include the portion of the borrowings for the salad production and warehousing facility in the Midwest that has been placed into service. The facility is being constructed under a build-to-suit lease with the construction in progress liability included in "Accrued liabilities" and "Other liabilities" on the Condensed Consolidated Balance Sheets and then reclassified to capital lease obligation as the related leased assets are placed into service. See further description of the build-to-suit lease below.