Legal Contingencies
12 Months Ended
Jan. 31, 2015
Commitments and Contingencies Disclosure [Abstract]  
Legal Contingencies

NOTE 12 – LEGAL CONTINGENCIES

In the normal course of business, the Company has pending claims and legal proceedings. It is the opinion of management, based on information available at this time, that none of the current claims and proceedings could have a material effect on the Company’s consolidated financial statements other than the matters discussed below. The material amounts of any legal fees expected to be incurred in connection with these matters are accrued when such amounts are estimable.

 

Altra Matters

GPS was the contractor for engineering, procurement and construction services related to an anhydrous ethanol plant in Carleton, Nebraska (the “Project”). The Project owner was ALTRA Nebraska, LLC (“Altra”). In November 2007, GPS and Altra agreed to a suspension of the Project while Altra sought to obtain financing to complete the Project. By March 2008, financing had not been arranged which terminated the construction contract prior to completion of the Project. In March 2008, GPS filed a mechanic’s lien against the Project in the approximate amount of $23.8 million, which amount included sums owed to subcontractors/suppliers of GPS and their subcontractors/suppliers. Several other claimants also filed mechanic’s liens against the Project.

In August 2009, Altra filed for bankruptcy protection. Proceedings resulted in a court-ordered liquidation of Altra’s assets. The incomplete plant was sold at auction in October 2009. Remaining net proceeds of approximately $5.5 million are being held by the bankruptcy court and have not been distributed to Altra’s creditors. The court separated the lien action into two phases relating to the priority of the claims first and the validity and amount of each party’s lien claim second. In November 2011, the court held that the claim of the project lender is superior to the lien claim of GPS. Fact discovery related to the second phase was completed in January 2012. After a court-imposed delay, summary judgement motions were submitted by the parties in April 2015. During a mediation session that occurred in April 2015, the parties with lien claims being considered by the bankruptcy court executed a memorandum of understanding including the terms of a settlement. Per its terms, the parties will execute a final written settlement agreement. Once that is completed, the Company should receive a payment of $1.6 million from the proceeds deposited with the bankruptcy court. The court was advised of the mediation result and the scheduled summary judgment hearings were cancelled.

In January 2009, GPS and Delta-T Corporation (“Delta T”), a major subcontractor to GPS on the Project, executed a Project Close-Out Agreement which settled all contract claims between the parties and included a payment in the amount of $3.5 million that GPS made to Delta-T. Pursuant to this agreement, Delta-T assigned its lien rights related to the Project to GPS which advised the parties that it would be pursuing only the assigned lien rights of Delta-T, amounting to approximately $21.2 million, for the remainder of this action.

In April 2009, a subcontractor to Delta-T (“DCR”) received an arbitration award in its favor against Delta-T in the amount of approximately $6.8 million that was confirmed in federal district court in Florida in December 2009. In April 2009, DCR also filed suit in the District Court of Thayer County, Nebraska, in order to recover its claimed amount of $6.8 million, as amended, from a payment bond issued to Altra on behalf of GPS. In December 2011, DCR filed a separate lawsuit against GPS relating to the Project in the District Court of Thayer County; its complaint sought damages in the amount of $6.1 million plus interest, costs and attorney fees.

In August 2012, the applicable parties executed settlement agreements that resulted in the dismissal of the claims against GPS and its surety company, with prejudice, and the assignment of DCR’s mechanic’s lien claim against the escrowed Altra Project sales proceeds to GPS. In connection with these settlements, GPS made cash payments to DCR in August 2012 that totaled $1,875,000. Subsequent to the execution of the settlement agreements and the payments made by GPS, DCR’s former counsel filed notice of a charging lien, claiming that DCR was indebted to counsel in excess of $1.8 million in fees and costs. In addition, a subcontractor to DCR on the Altra Project filed a motion asking the court to set aside the dismissals or, in the alternative, to reconsider them. In October 2012, the court vacated the prior orders of dismissal and permitted DCR’s former counsel and former subcontractor to file complaints. A trial for the charging lien and subcontractor claims was held in April 2013. On September 30, 2014, the court dismissed the complaints of the plaintiffs against GPS and its surety company, and subsequently issued orders of dismissal with prejudice bringing these actions to a close.