SUBSEQUENT EVENT
6 Months Ended
Jul. 31, 2019
SUBSEQUENT EVENT  
SUBSEQUENT EVENT

NOTE 15 – SUBSEQUENT EVENT

 

On August 29, 2019, GPS received full notice to proceed with EPC activities under a contract for a 1,875 MW natural gas-fired power plant that will be built in Guernsey County, Ohio. Construction of this state-of-the-art combined cycle facility has begun with completion scheduled in 2022.