NOTE 11 – CONTINGENCIES

 

In the normal course of business, the Company may have pending claims and legal proceedings. It is the opinion of management, based on information available at this time, that there are no current claims and proceedings that could have a material adverse effect on the Company’s consolidated financial statements other than as described below. The material amounts of any legal fees expected to be incurred in connection with legal matters are accrued when such amounts are estimable.

 

Legal Matters

 

On February 1, 2016, TRC was sued in Person County, North Carolina, by a subcontractor, PPS Engineers, Inc. (“PPS”), in an attempt to force TRC to pay invoices for services rendered in the total amount of $2.3 million. In addition, PPS placed liens on the property of customers in several states where work was performed by PPS and it also filed a claim in Tennessee against the bond issued on behalf of TRC relating to one significant project located there. On March 4, 2016, TRC filed responses to the claims of PPS, asserting that PPS failed to deliver a number of items required by the applicable contract between the parties, that the invoices rendered by PPS covering the disputed services would not be paid until such deliverables were supplied, and that certain sums were owed to it by PPS for services, furniture, fixtures, equipment, and software that were supplied by TRC on behalf of PPS. The amounts invoiced by PPS were accrued by TRC and the corresponding liability amounts were included in accounts payable in the consolidated balance sheet as January 31, 2018. TRC did not record an account receivable for the amounts it believed were owed to it by PPS. A mediation effort was attempted in 2016 but it was unproductive in resolving the disputes. In December 2017, an amended complaint was filed by the plaintiff. TRC filed an amended counterclaim and the discovery process began. In July 2018, the parties agreed to a settlement of all claims made against each other with TRC agreeing to make a payment to PPS in the amount of $0.9 million. As the total of the previously accrued amounts exceeded the negotiated settlement amount, the Company recorded a gain on the settlement in the amount of $1.4 million that is included in other income for Fiscal 2019.

 

GPS was in a dispute with a former subcontractor on one of its power plant construction projects that was settled pursuant to binding arbitration in June 2018. The arbitration panel awarded approximately $5.2 million, plus interest and arbitration fees, to the subcontractor. The substantial portion of the total amount, which was paid by GPS to the subcontractor in July 2018, was charged to cost of revenues. In connection with the settlement, the legal claims made by the parties against each other were dismissed with prejudice and without costs to the parties, all liens filed by the subcontractor related to the project were released, and each party provided the other with a release from future claims related to this matter.

 

In January 2019, GPS filed a lawsuit against Exelon West Medway II, LLC and Exelon Generation Company, LLC (together referred to as “Exelon”) for Exelon’s breach of contract and failure to remedy various conditions which negatively impacted the schedule and the costs associated with the construction by GPS of a gas-fired power plant for Exelon in Massachusetts. As a result, Exelon has received the benefits of the construction without making payments to GPS for the value received. On March 7, 2019, Exelon provided GPS with a notice intending to terminate the EPC contract under which GPS had been providing services to Exelon. At that time, the construction project was nearly complete and both of the power generation units included in the plant successfully reached first fire. The completion of various prescribed performance tests and the clearance of punch-list items were the primary tasks necessary to be accomplished by GPS in order to achieve substantial completion of the power plant. Nevertheless and among other actions, Exelon has provided contractual notice requiring GPS to vacate the construction site, has made claims against GPS and has withheld payments from GPS on invoices rendered to Exelon in accordance with the terms of the EPC contract between the parties. With vigor, GPS intends to assert its rights under the EPC contract, to pursue the collection from Exelon of amounts owed under the contract and to defend itself against the allegations that GPS has not performed in accordance with the contract.

 

Self-Insurance

 

TRC has elected to retain portions of future losses, if any, through the loss retention features of certain insurance policies and the use of self-insurance for exposures related to worker’s compensation and certain employee health insurance claims. Liabilities in excess of contractually limited amounts are the responsibility of an insurance carrier. To the extent that the Company retains the risks for these exposures, including claims incurred but not reported, liabilities have been accrued based upon the Company’s best estimates, with input from legal and insurance advisors. Changes in assumptions, as well as changes in actual experience, could cause these estimates to change in the near-term. Management believes that reasonably possible losses, if any, for these matters, to the extent not otherwise disclosed and net of recorded accruals, will not have a material adverse effect on the Company’s future results of operations, financial position or cash flow. At January 31, 2019 and 2018, the aggregate amounts established to cover self-insured and other retained losses were included in the balances of accrued expenses in the consolidated balance sheets. Beginning in calendar year 2017, the employee health benefits for the employees of TRC were fully insured.

 

Warranty Costs

 

Many of the Company’s construction contracts contain warranty provisions covering defects in equipment, materials, design or workmanship that typically run from nine to twenty-four months after the completion of construction. Because of the nature of the Company’s projects, including project owner inspections of the work both during construction and prior to substantial completion, the Company has not experienced material unexpected warranty costs. However, provision for estimated warranty costs, if any, is made in the period in which such costs become probable. The corresponding liabilities are periodically adjusted to reflect actual experience. Warranty costs are estimated based on the Company’s experience with the type of work and any known risks relative to each completed project. At January 31, 2019 and 2018, the amounts established to cover future warranty costs under completed EPC contracts were included as contract liabilities in the consolidated balance sheets.

 

Performance Bonds

 

In the ordinary course of business, customers may request that the Company obtain surety bonds in connection with construction contract performance obligations. The Company would be obligated to reimburse the issuer of such surety bonds for any payments made. Each of our commitments under performance bonds generally ends concurrently with the expiration of the related contractual obligation. From time to time, GPS arranges for bonding to be issued by the Company’s surety firm for the benefit of an owner of an energy project for which GPS is generally not providing construction services. GPS collects fees from the project owner as consideration for the use of the Company’s bonding capacity. As of January 31, 2019 and 2018, the amount of outstanding surety bonds issued under such arrangements was $11.1 million.