NOTE 9 — LEGAL MATTERS

 

In the normal course of business, the Company may have pending claims and legal proceedings. It is the opinion of management, based on information available at this time, that there are no current claims and proceedings that could have a material effect on the Company’s condensed consolidated financial statements.

 

On February 1, 2016, TRC was sued in Person County, North Carolina, by a subcontractor, PPS Engineers, Inc. (“PPS”), in an attempt to force TRC to pay invoices for services rendered in the total amount of $2.3 million. In addition, PPS placed liens on the property of customers in several states where work was performed by PPS and it also filed a claim in Tennessee against the bond issued on behalf of TRC relating to one significant project located there. On March 4, 2016, TRC filed responses to the claims of PPS, asserting that PPS failed to deliver a number of items required by the applicable contract between the parties, that the invoices rendered by PPS covering the disputed services would not be paid until such deliverables were supplied, and that certain sums were owed to it by PPS for services, furniture, fixtures, equipment, and software that were supplied by TRC on behalf of PPS. The amounts invoiced by PPS were accrued by TRC and the corresponding liability amounts were included in accounts payable in the condensed consolidated balance sheet as January 31, 2018. TRC did not record an account receivable for the amounts it believes are owed to it by PPS. A mediation effort was attempted in 2016 but it was unproductive in resolving the disputes. In December 2017, an amended complaint was filed by the plaintiff and TRC filed an amended counterclaim and the discovery process began.

 

In July 2018, the parties agreed to a settlement of all claims made against each other with TRC agreeing to make a payment to PPS in the amount of $0.9 million. As the total of the previously accrued amounts exceeded the negotiated settlement amount, the Company recorded a gain on the settlement in the amount of $1.4 million that is included in other income for the periods ended July 31, 2018.

 

GPS was in a dispute with a former subcontractor on one of its power plant construction projects that was settled pursuant to binding arbitration in June 2018. The arbitration panel awarded approximately $5.2 million, plus interest and arbitration fees, in favor of the subcontractor. The total amount was paid by GPS to the subcontractor in July 2018 and, except for the portion of interest that accrued in the second quarter, was accrued by the Company as of April 30, 2018. In connection with the settlement, the legal claims made by the parties against each other were dismissed with prejudice and without costs to the parties, all liens filed by the subcontractor related to the project were released, and each party provided the other with a release from future claims related to this matter.