NOTE 15 — SUBSEQUENT EVENT
Subsequent to July 31, 2011, the owner of the completed energy plant project in Connecticut agreed to previously disputed change orders in the approximate amount of $1.74 million which have been invoiced to the customer and will be reflected in the Company’s net revenues in the third quarter of the current fiscal year. The direct costs associated with the change orders were expensed as incurred and included in the estimated total cost of the completed contract as of July 31, 2011.