Commitments And Contingencies (Environmental Remediation Contingencies) (Details) (USD $)
3 Months Ended9 Months Ended
Sep. 30, 2011
Sep. 30, 2011
Dec. 31, 2010
Pacific Gas And Electric Company [Member] | Remediation At Utility Natural Gas Compressor Site Near Hinkley, CA [Member]
   
Long-term Purchase Commitment [Line Items]   
Amount of environmental loss accrual for remediation$ 150,000,000$ 150,000,000 
Remediation At Utility Natural Gas Compressor Site Near Topock, AZ [Member]
   
Long-term Purchase Commitment [Line Items]   
Amount of environmental loss accrual for remediation178,000,000178,000,000 
Remediation At Divested Generation Facilities [Member]
   
Long-term Purchase Commitment [Line Items]   
Amount of environmental loss accrual for remediation81,000,00081,000,000 
Remediation Costs For Generation And Other Facilities And For Third-Party Disposal Sites [Member]
   
Long-term Purchase Commitment [Line Items]   
Amount of environmental loss accrual for remediation140,000,000140,000,000 
Investigation And Or Remediation Costs At Former MGP Sites [Member]
   
Long-term Purchase Commitment [Line Items]   
Amount of environmental loss accrual for remediation157,000,000157,000,000 
Remediation Of Decommissioning Fossil Fueled Sites [Member]
   
Long-term Purchase Commitment [Line Items]   
Amount of environmental loss accrual for remediation57,000,00057,000,000 
Pacific Gas And Electric Company [Member] | Hinkley Natural Gas Compressor Station [Member]
   
Long-term Purchase Commitment [Line Items]   
Authorized recovery of hazardous waste remediation costs90.00%90.00% 
Hinkley Natural Gas Compressor Station [Member]
   
Long-term Purchase Commitment [Line Items]   
Gross environmental remediation liability150,000,000150,000,00045,000,000
Utility undiscounted future costs150,000,000150,000,00045,000,000
provision for environmental remediation106,000,000132,000,000 
Pacific Gas And Electric Company [Member]
   
Long-term Purchase Commitment [Line Items]   
Gross environmental remediation liability763,000,000763,000,000612,000,000
Amount of environmental loss accrual expected to be recovered364,000,000364,000,000 
Amounts recoverable by Utility as authorized by CPUC and FERC128,000,000128,000,000 
Recovery of remediation costs for decommissioning fossil-fueled sites 100.00% 
Increase in undiscounted future costs in the event other potentially responsible parties are not able to contribute1,400,000,0001,400,000,000 
Utility undiscounted future costs$ 763,000,000$ 763,000,000$ 612,000,000