Chapter 11 Proceedings

On the Petition Date, PG&E Corporation and the Utility filed voluntary petitions for relief under Chapter 11 in the Bankruptcy Court. PG&E Corporation's and the Utility’s Chapter 11 Cases are being jointly administered under the caption In re: PG&E Corporation and Pacific Gas and Electric Company, Case No. 19-30088 (DM).

PG&E Corporation and the Utility continue to operate their businesses as debtors in possession under the jurisdiction of the Bankruptcy Court and in accordance with applicable provisions of the Bankruptcy Code and the orders of the Bankruptcy Court. As debtors in possession, PG&E Corporation and the Utility are authorized to continue to operate as ongoing businesses, and may pay all debts and honor all obligations arising in the ordinary course of their businesses after the Petition Date. However, PG&E Corporation and the Utility may not pay third-party claims or creditors on account of obligations arising before the Petition Date or engage in transactions outside the ordinary course of business without approval of the Bankruptcy Court.

Under the Bankruptcy Code, third-party actions to collect pre-petition indebtedness owed by PG&E Corporation or the Utility, as well as most litigation pending against PG&E Corporation and the Utility (including the third-party matters described in Note 13 above), are subject to an automatic stay. Absent an order of the Bankruptcy Court providing otherwise, substantially all pre-petition liabilities will be administered under a Chapter 11 plan of reorganization to be voted upon by creditors and other stakeholders, and approved by the Bankruptcy Court. However, under the Bankruptcy Code, regulatory or criminal proceedings are generally not subject to an automatic stay, and PG&E Corporation and the Utility expect these proceedings to continue during the pendency of the Chapter 11 Cases.

To assure ordinary course operations, on January 31, 2019, PG&E Corporation and the Utility received interim approval from the Bankruptcy Court on a variety of “first day” motions, including motions that authorize them to maintain their existing cash management system, to continue wage and salary payments and other benefits to their employees, to secure debtor in possession financing and other customary relief. On February 27, 2019, PG&E Corporation and the Utility received final approval of the first day motion to continue wage and salary payments and other benefits to their employees (with one limited objection with respect to a discrete matter having been preserved by the Bankruptcy Court) and certain other first day motions for customary relief. Hearings on certain other first day motions, including a hearing to consider final approval of PG&E Corporation’s and the Utility’s motions to continue their existing cash management system and to approve their debtor in possession financing, have not been held and no assurances can be given that the Bankruptcy Court will approve such motions on a final basis. PG&E Corporation and the Utility are unable to predict the date of the final hearing with respect to such motions, but there are hearings currently scheduled for March 12, March 13 and March 27, 2019.

In connection with the Chapter 11 Cases, PG&E Corporation and the Utility entered into the DIP Credit Agreement. See Note 4 above for a description of the DIP Credit Agreement.

The commencement of the Chapter 11 Cases constituted an event of default or termination event, and caused an automatic and immediate acceleration of the Accelerated Direct Financial Obligations. Accordingly, as a result of the commencement of the Chapter 11 Cases, the principal amount of the Accelerated Direct Financial Obligations, together with accrued interest thereon, and in case of certain indebtedness, premium, if any, thereon, immediately became due and payable. However, any efforts to enforce such payment obligations are automatically stayed as of the Petition Date, and are subject to the applicable provisions of the Bankruptcy Code and orders of the Bankruptcy Court. The material Accelerated Direct Financial Obligations include the outstanding senior notes, agreements in respect of certain series of pollution control bonds, and PG&E Corporation's term loan facility, as well as short-term borrowings under PG&E Corporation's and the Utility's revolving credit facilities and the Utility's term loan facility disclosed in Note 4 above. The filing of the Chapter 11 Cases may also provide the counterparties under certain commodity and related agreements with the right to declare an event of default and to seek termination of such rights subject to the applicable provisions of the Bankruptcy Code and orders of the Bankruptcy Court.

Under the priority scheme established by the Bankruptcy Code, certain post-petition and secured or “priority” pre-petition liabilities need to be satisfied before general unsecured creditors and holders of PG&E Corporation's and the Utility’s equity are entitled to receive any distribution. No assurance can be given as to what values, if any, will be ascribed in the Chapter 11 Cases to the claims and interests of each of these constituencies. Additionally, no assurance can be given as to whether, when or in what form unsecured creditors and holders of PG&E Corporation’s or the Utility’s equity may receive a distribution on such claims or interests.

Under the Bankruptcy Code, PG&E Corporation and the Utility may assume, assume and assign, or reject certain executory contracts and unexpired leases, including, without limitation, leases of real property and equipment, subject to the approval of the Bankruptcy Court and to certain other conditions. Any description of an executory contract or unexpired lease in this Annual Report on Form 10-K, including, where applicable, the express termination rights thereunder or a quantification of their obligations, must be read in conjunction with, and is qualified by, any overriding rejection rights PG&E Corporation and the Utility have under the Bankruptcy Code.

As of February 28, 2019, the Utility had outstanding borrowings of $350 million under the DIP Revolving Facility and $30 million in face amount of outstanding letters of credit, with remaining availability of $1.12 billion under the DIP Revolving Facility.

US District Court Matters and Probation

On August 9, 2016, the jury in the federal criminal trial against the Utility in the United States District Court for the Northern District of California, in San Francisco, found the Utility guilty on one count of obstructing a federal agency proceeding and five counts of violations of pipeline integrity management regulations of the Natural Gas Pipeline Safety Act. On January 26, 2017, the court issued a judgment of conviction against the Utility. The court sentenced the Utility to a 5-year corporate probation period, oversight by a third-party monitor for a period of five years, with the ability to apply for early termination after 3 years, a fine of $3 million to be paid to the federal government, certain advertising requirements, and community service.

The probation includes a requirement that the Utility not commit any local, state, or federal crimes during the probation period. As part of the probation, the Utility has retained a third-party monitor at the Utility’s expense. The goal of the third-party monitor is to help ensure that the Utility takes reasonable and appropriate steps to maintain the safety of its gas and electric operations, and to maintain effective ethics, compliance and safety related incentive programs on a Utility-wide basis.

On November 27, 2018, the court overseeing the Utility’s probation, issued an order requiring that the Utility, the United States Attorney’s Office for the Northern District of California (the “USAO”) and the third-party monitor provide written answers to a series of questions regarding the Utility’s compliance with the terms of its probation, including what requirements of the Utility’s probation “might be implicated were any wildfire started by reckless operation or maintenance of PG&E power lines” or “might be implicated by any inaccurate, slow, or failed reporting of information about any wildfire by PG&E.”  The court also ordered the Utility to provide “an accurate and complete statement of the role, if any, of PG&E in causing and reporting the recent 2018 Camp fire in Butte County and all other wildfires in California” since January 2017 (“Question 4 of the November 27 Order”).  On December 5, 2018, the court issued an order requesting that the Office of the California Attorney General advise the court of its view on “the extent to which, if at all, the reckless operation or maintenance of PG&E power lines would constitute a crime under California law.”  The responses of the Attorney General were submitted on December 28, 2018, and the responses of the Utility, the USAO and the third-party monitor were submitted on December 31, 2018.

On January 3, 2019, the court issued a new order requiring that the Utility provide further information regarding the Atlas fire.  The court noted that “[t]his order postpones the question of the adequacy of PG&E’s response” to Question 4 of the November 27 Order.  On January 4, 2019, the court issued another order requiring that the Utility provide “with respect to each of the eighteen October 2017 Northern California wildfires that [Cal Fire] has attributed to [the Utility’s] facilities,” information regarding the wind conditions in the vicinity of each fire’s origin and information about the equipment allegedly involved in each fire’s ignition.  The responses of the Utility were submitted on January 10, 2019.

On January 9, 2019, the court ordered the Utility to appear in court on January 30, 2019, as a result of the court’s finding that “there is probable cause to believe there has been a violation of the conditions of supervision” with respect to reporting requirements related to the 2017 Honey fire.  In addition, on January 9, 2019, the court issued an order (the “January 9 Order”) proposing to add new conditions of probation that would require the Utility, among other things, to:

prior to June 21, 2019, “re-inspect all of its electrical grid and remove or trim all trees that could fall onto its power lines, poles or equipment in high-wind conditions, . . . identify and fix all conductors that might swing together and arc due to slack and/or other circumstances under high-wind conditions[,] identify and fix damaged or weakened poles, transformers, fuses and other connectors [and] identify and fix any other condition anywhere in its grid similar to any condition that contributed to any previous wildfires”,

“document the foregoing inspections and the work done and . . . rate each segment’s safety under various wind conditions” and

at all times from and after June 21, 2019, “supply electricity only through those parts of its electrical grid it has determined to be safe under the wind conditions then prevailing.”

The Utility was ordered to show cause by January 23, 2019, as to why the Utility’s conditions of probation should not be modified as proposed. The Utility's response was submitted on January 23, 2019. The court requested that Cal Fire file a public statement, and invited the CPUC to comment, by January 25, 2019. On January 30, 2019, the court found that the Utility had violated a condition of its probation with respect to reporting requirements related to the 2017 Honey fire. The court issued an order stating that a sentencing hearing on the probation violation will be set at a later date. The court also invited parties to comment by February 20, 2019, on the 2019 Wildfire Safety Plan that the Utility submitted to the CPUC on February 6, 2019.