XML 73 R45.htm IDEA: XBRL DOCUMENT v3.19.1
Regulatory Matters - Nuclear Construction Cost and Schedule (Details) - GEORGIA POWER CO - Plant Vogtle Units 3 And 4
$ in Millions
3 Months Ended
Mar. 31, 2019
USD ($)
Loss Contingencies [Line Items]  
Base project capital cost forecast $ 8,000
Construction contingency estimate 400
Total project capital cost forecast 8,400
Net investment as of March 31, 2019 (4,900)
Remaining estimate to complete 3,500
Expected capitalized costs 325
Guarantor obligations 1,700
Customer refund $ 188