12.Commitments and Contingencies

 

Significant new commitments, material changes in commitments and ongoing contingencies as of June 30, 2014, not disclosed elsewhere, are as follows:

 

Compensation ArrangementsCash Performance Unit Awards. The Compensation Committee has approved various grants of performance unit awards to certain officers and employees, to be settled in cash, based on the achievement of certain stipulated goals, all of which are described in detail in the Form 10-K (including fiscal 2014 grants made during the December 2013 quarter). Since September 30, 2013, there have been no significant changes in Headwaters’ commitments or in the amounts accrued under these awards, except for the payment during the December 2013 quarter of amounts contractually due under the terms of certain prior year awards, and the accrual of approximately $2.0 million in the June 2014 quarter under terms of the fiscal 2014 grants. Headwaters currently expects that additional amounts will be earned during the September 2014 quarter under the terms of the fiscal 2014 awards.

 

Cash-Settled SAR Grants.  In fiscal 2011, the Committee approved grants to certain employees of approximately 0.4 million cash-settled SARs, approximately 0.1 million of which remain outstanding as of June 30, 2014. These SARs vested in annual installments through September 30, 2013, provided the participant was still employed by Headwaters at the respective vest dates, and are settled in cash upon exercise by the employee. The SARs terminate on September 30, 2015 and must be exercised on or before that date. As of June 30, 2014, approximately $1.2 million has been accrued for outstanding awards because the stock price at June 30, 2014 was above the grant-date stock price of $3.81. Future changes in Headwaters’ stock price in any amount above $3.81 through September 30, 2015 will result in adjustment to the expected remaining liability, which adjustment (whether positive or negative) will be reflected in Headwaters’ consolidated statement of operations each quarter.

 

In fiscal 2012, the Committee approved grants to certain officers and employees of approximately 1.0 million cash-settled SARs, approximately 0.4 million of which remain outstanding as of June 30, 2014. These SARs have terms similar to those described above, except they could not vest until and unless the 60-day average stock price exceeded approximately 135% of the stock price on the date of grant (or $2.50), which occurred during 2012. Approximately $5.0 million has been accrued for outstanding awards as of June 30, 2014. Changes in Headwaters’ stock price in any amount above the grant-date stock price of $1.85 through September 30, 2016, the date these SARs expire, will result in adjustment to the expected remaining liability, which adjustment (whether positive or negative) will be reflected in Headwaters’ statement of operations each quarter. Compensation expense for all cash-settled SARs was approximately $3.9 million and $5.1 million for the nine months ended June 30, 2013 and 2014, respectively.

 

Property, Plant and Equipment — As of June 30, 2014, Headwaters was committed to spend approximately $5.7 million on capital projects that were in various stages of completion.

 

Legal Matters — Headwaters has ongoing litigation and asserted claims which have been incurred during the normal course of business, including the specific matters discussed below. Headwaters intends to vigorously defend or resolve these matters by settlement, as appropriate. Management does not currently believe that the outcome of these matters will have a material adverse effect on Headwaters’ operations, cash flow or financial position.

 

Headwaters incurred approximately $1.8 million and $4.5 million of expense for legal matters during the nine months ended June 30, 2013 and 2014, respectively. Historically, except for fiscal 2011 and fiscal 2014, when $15.0 million and $2.5 million, respectively, of charges were accrued for potential losses, costs for outside legal counsel have comprised a majority of Headwaters’ litigation-related costs. Headwaters currently believes the range of potential loss for all unresolved legal matters, excluding costs for outside counsel, is from $2.5 million up to the amounts sought by claimants and has recorded a liability as of June 30, 2014 of $2.5 million. The substantial claims and damages sought by claimants in excess of this amount are not currently deemed to be probable. Headwaters’ outside counsel and management currently believe that unfavorable outcomes of outstanding litigation beyond the amount accrued are neither probable nor remote. Accordingly, management cannot express an opinion as to the ultimate amount, if any, of Headwaters’ liability, nor is it possible to estimate what litigation-related costs will be in future periods.

 

The specific matters discussed below raise difficult and complex legal and factual issues, and the resolution of these issues is subject to many uncertainties, including the facts and circumstances of each case, the jurisdiction in which each case is brought, and the future decisions of juries, judges, and arbitrators. Therefore, although management believes that the claims asserted against Headwaters in the named cases lack merit, there is a possibility of material losses in excess of the amounts accrued if one or more of the cases were to be determined adversely against Headwaters for a substantial amount of the damages asserted. It is possible that a change in the estimates of probable liability could occur, and the changes could be material. Additionally, as with any litigation, these proceedings require that Headwaters incur substantial costs, including attorneys’ fees, managerial time and other personnel resources, in pursuing resolution.

 

AES Thames Bankruptcy.  Headwaters Resources, Inc. (HRI) had a contract to perform fly ash disposal services for AES Thames, L.L.C. (AES Thames) related to its coal-fired power plant located in Montville, Connecticut. AES Thames filed a petition for relief under the United States Bankruptcy Code in February 2011. In January 2013, the trustee filed an adversary proceeding complaint in the United States Bankruptcy Court for the District of Delaware alleging that certain payments made before the bankruptcy by AES Thames to HRI were avoidable preferential transfers under the Bankruptcy Code. The complaint seeks to recover $1.6 million plus interest, attorney fees, and costs. HRI answered denying the allegations of the complaint. In May 2014, HRI and the trustee entered a stipulation of settlement dismissing the trustee’s claims against HRI in exchange for a payment by HRI of $25,000 and a release of HRI’s claims in the bankruptcy, bringing the case to conclusion.

 

Edwards.  In May 2013, James W. Edwards, purportedly a stockholder of Headwaters Incorporated, filed a complaint in the United States District Court for the District of Utah against current and former members of the Board of Directors of the Company and against Headwaters Incorporated. The complaint alleges that the Board breached its fiduciary duties and wasted corporate assets in connection with the Compensation Committee’s grant of certain stock appreciation rights to the Company’s Chief Executive Officer in November 2011 under the 2010 Incentive Plan (Plan). The complaint alleges that the 2011 grant exceeded Plan limits and that the 2013 Proxy Statement in connection with the Company’s 2013 Annual Meeting of Stockholders contained false and misleading information concerning the 2011 grant. The complaint seeks an order rescinding the 2011 grant, unspecified damages and other remedies, plus interest, attorney fees, and costs. The complaint was brought derivatively on behalf of Headwaters Incorporated and as a purported class action on behalf of all shareholders of record as of December 31, 2012. Defendants filed their initial response to the complaint in January 2014. The parties entered into a stipulation of settlement in February 2014 and in May 2014 the District Court entered an order granting preliminary approval of settlement. Headwaters has published notice of the proposed settlement. It is expected that the District Court will hold a hearing on motion for final approval of the settlement in August 2014. Because resolution of the litigation is uncertain, legal counsel and management cannot express an opinion as to the ultimate amount, if any, of Headwaters’ liability.

 

Boynton.  In 1998, Headwaters entered into a technology purchase agreement with James G. Davidson and Adtech, Inc. The transaction transferred certain patent and royalty rights to Headwaters related to a synthetic fuel technology invented by Davidson. In 2002, Headwaters received a summons and complaint from the United States District Court for the Western District of Tennessee filed by former stockholders of Adtech alleging, among other things, fraud, conspiracy, constructive trust, conversion, patent infringement and interference with contract arising out of the 1998 technology purchase agreement entered into between Davidson and Adtech on the one hand, and Headwaters on the other. All claims against Headwaters were dismissed in pretrial proceedings except claims of conspiracy and constructive trust. The District Court certified a class comprised of substantially all purported stockholders of Adtech, Inc. The plaintiffs sought compensatory damages from Headwaters in the approximate amount of $43.0 million plus prejudgment interest and punitive damages. In June 2009, a jury reached a verdict in a trial in the amount of $8.7 million for the eight named plaintiffs representing a portion of the class members. In September 2010, a jury reached a verdict after a trial for the remaining 46 members of the class in the amount of $7.3 million. In April 2011, the trial court entered an order for a constructive trust in the amount of approximately $16.0 million (the same amount as the sum of the previous jury verdicts), and entered judgment against Headwaters in the total approximate amount of $16.0 million, in accordance with the verdicts and order on constructive trust. Headwaters and plaintiffs cross-appealed from the judgment to the United States Court of Appeals for the Federal Circuit. The Federal Circuit transferred the case to the United States Court of Appeals for the Sixth Circuit on the basis of jurisdiction. In April 2014, a panel of the Sixth Circuit affirmed the judgment of the District Court in a divided decision. In May 2014, Headwaters paid the plaintiffs approximately $16.2 million in exchange for a satisfaction of judgment, bringing the case to conclusion.

 

EPA.  In April 2012, Headwaters Resources, Inc. (HRI) filed a complaint in the United States District Court for the District of Columbia against the United States Environmental Protection Agency (EPA). The complaint alleges that the EPA has failed to review, and where necessary, revise RCRA subtitle D regulations applicable to the disposal of coal ash within the timeframe required by statute. Other parties also initiated litigation against the EPA alleging the same (and other) failures of the EPA to perform its duties regarding coal ash disposal regulations. HRI’s complaint seeks certain declaratory relief with respect to EPA rulemaking at issue in the case. The District Court consolidated HRI’s case with related actions brought by other parties. In October 2013, the District Court granted summary judgment that the EPA has failed to fulfill its statutory duty to review coal ash disposal regulations, among other things, ordering the EPA to propose a schedule to complete its review of coal ash disposal regulations, and, as necessary, revise the regulations. The parties filed a proposed schedule for the EPA to review its coal ash disposal regulations by December 2014, which schedule is expected to be approved by the District Court. How the EPA will revise its coal ash regulations will not be known until the EPA issues its final regulations. Because the final resolution of the litigation is uncertain, legal counsel and management cannot express an opinion as to the ultimate outcome.

 

Fentress Families Trust.  VFL Technology Corporation (VFL), acquired by HRI in 2004, provides services related to fly ash management to Virginia Electric and Power Company. In February 2012, 383 plaintiffs, most of whom are residents living in the City of Chesapeake, Virginia, filed a complaint in the State of Virginia Chesapeake Circuit Court against 15 defendants, including Virginia Electric and Power Company (VEPCO), and certain other persons associated with the Battlefield Golf Course, including owners, developers, contractors, and others, including VFL and Headwaters, alleging causes of action for nuisance and negligence. The complaint alleges that fly ash used to construct the golf course was carried in the air and contaminated water exposing plaintiffs to dangerous chemicals and causing property damage. Plaintiffs’ complaint seeks injunctive relief and damages of approximately $850.0 million for removal and remediation of the fly ash and the water supply, $1.9 billion for vexation, $8.0 million and other unspecified amounts for personal injuries, and $55.0 million as damages to properties, plus prejudgment interest, attorney fees, and costs. In a related case, other plaintiffs have filed a separate lawsuit asserting the same claims against the same defendants claiming additional damages totaling approximately $307.2 million. In August 2013 the court ruled on VEPCO’s demurrer ordering that claims for personal injury or property damage based upon allegations of groundwater contamination were dismissed but that claims of nuisance and negligence based upon allegations of air-borne ash and contaminated surface water would not be dismissed. These cases are based on substantially the same alleged circumstances asserted in complaints filed by the plaintiffs in 2009 and voluntarily dismissed in 2010. Discovery is underway. HRI has filed claims for defense and indemnity with several of its insurers. In 2010, HRI filed suit in the United States District Court for the District of Utah against two insurers that denied coverage based on allegations in the 2009 Fentress complaints. The District Court ruled in the insurers’ favor, which ruling HRI appealed to the United States Court of Appeals for the Tenth Circuit. The parties have completed appellate briefing and oral argument was held in January 2014 but no decision has been announced. Another insurer continues to pay for the defense of the underlying cases under a reservation of rights. The relatively novel fly ash claims of the plaintiffs together with multiple insurance policies and policy periods make insurance coverage issues complex and uncertain. Moreover, plaintiffs’ total claims exceed the potential limits of insurance available to HRI. Because resolution of the litigation is uncertain, legal counsel and management cannot express an opinion as to the ultimate amount, if any, of HRI’s liability, or the insurers’ obligation to indemnify HRI against loss, if any.

 

CPM.  In December 2012, CPM filed a complaint in the State of Virginia Chesapeake Circuit Court against HRI related to construction of the golf course described in the Fentress Families Trust case, alleging breach of contract and seeking declaratory judgment and compensatory damages in the amount of $0.5 million plus attorney fees and costs. CPM alleges that HRI should indemnify CPM for past and future expenses incurred in defending against the Fentress complaints. Because resolution of this litigation is uncertain, legal counsel and management cannot express an opinion as to the ultimate amount, if any, of HRI’s liability, or the insurers’ obligation to indemnify HRI against loss, if any.

 

Archstone.  Archstone owns an apartment complex in Westbury, New York. Archstone alleges that moisture penetrated the building envelope and damaged moisture sensitive parts of the buildings which began to rot and grow mold. In 2008, Archstone evicted its tenants and began repairing the 21 apartment buildings. Also in 2008, Archstone filed a complaint in the Nassau County Supreme Court of the State of New York against the prime contractor and its performance bond surety, the designer, and Eldorado Stone, LLC which supplied architectural stone that was installed by others during construction. The prime contractor then sued over a dozen subcontractors who in turn sued others. Most parties filed cross-claims for contribution and indemnity against Eldorado Stone and others. Archstone claims as damages approximately $36.0 million in repair costs, $19.0 million in lost lease payments and rent abatement, $7.0 million paid to tenants who sued Archstone, and $7.0 million for class action defense fees, plus prejudgment interest and attorney’s fees. Eldorado Stone answered denying liability and tendered the matter to its insurers who are paying for the defense of the case. Eldorado Stone obtained an order of summary judgment dismissing three of Archstone’s four claims. Eldorado Stone has moved for summary judgment on Archstone’s remaining claim of common law indemnification for damages paid to the tenants and associated attorney’s fees. Meanwhile, discovery is underway. Because the resolution of the action is uncertain, legal counsel and management cannot express an opinion concerning the likely outcome of this matter, the liability of Eldorado Stone, if any, or the insurers’ obligation to indemnify Eldorado Stone against loss, if any.

 

Headwaters Building Products Matters.  There are litigation and pending and threatened claims made against certain subsidiaries of Headwaters Building Products (HBP), a division within Headwaters’ light building products segment, with respect to several types of exterior finish systems manufactured and sold by its subsidiaries for application by contractors on residential and commercial buildings. The plaintiffs or claimants in these matters typically allege that the structures have suffered damage from water penetration due to some alleged failure of the building product or wall system. The claims involve alleged liabilities associated with certain stucco and architectural stone products which are produced and sold by certain subsidiaries of HBP. The Archstone case summarized above is an example of these types of claims.

 

The foregoing litigation and claims typically cite damages for alleged personal injuries, property damage, economic loss, unfair business practices and punitive damages. Claims made against Headwaters and its subsidiaries generally have been paid by their insurers, subject to Headwaters’ payment of deductibles or self-insured retentions, although such insurance carriers typically have issued “reservation of rights” letters. There is no guarantee of insurance coverage or continuing coverage. These and future proceedings may result in substantial costs to Headwaters and HBP, including attorneys’ fees, managerial time and other personnel resources and costs. Adverse resolution of these proceedings could have a materially negative effect on Headwaters’ businesses, financial condition, and results of operation, and its ability to meet its financial obligations. Although Headwaters carries general and product liability insurance, subject to exclusions and self-insured retentions, Headwaters cannot assure that such insurance coverage will remain available, that Headwaters’ insurance carriers will accept claims or will remain viable, or that the insured amounts will cover all claims in excess of self-insured retentions. Future rate increases may also make such insurance uneconomical for Headwaters to maintain. Because resolution of the litigation and claims is uncertain, legal counsel and management cannot express an opinion as to the ultimate amount, if any, of HBP’s liability.

 

Heavy Construction Materials MattersIn addition, there are litigation and pending and threatened claims made against HRI, Headwaters’ Heavy Construction Materials segment, with respect to coal combustion products. The plaintiffs or claimants in these matters have alleged that inhalation or other exposure to fly ash is unsafe and that HRI has failed to warn about the alleged dangers of fly ash exposure and the use of adequate protection. The Fentress Family Trust case summarized above is an example of these types of claims. The application of relatively novel fly ash claims to insurance policies is complex and uncertain. Adverse resolution of these proceedings could have a materially negative effect on Headwaters’ businesses, financial condition, and results of operation, and its ability to meet its financial obligations. Because resolution of the litigation, claims, and insurance coverage disputes is uncertain, legal counsel and management cannot express an opinion as to the ultimate amount, if any, of HRI’s liability.

 

Other.  Headwaters and its subsidiaries are also involved in other legal proceedings that have arisen in the normal course of business. Because resolution of these proceedings is uncertain, legal counsel and management cannot express an opinion as to the ultimate amount, if any, of Headwaters’ liability.