XML 74 R35.htm IDEA: XBRL DOCUMENT v3.22.2
Rate And Regulatory Matters (Narrative-Illinois) (Details) - Ameren Illinois Company
$ in Millions
6 Months Ended
Jun. 30, 2022
USD ($)
numberOfProposedPerformanceMetrics
Rate And Regulatory Matters [Line Items]  
Annual investment in energy-efficiency programs $ 120
Minimum  
Rate And Regulatory Matters [Line Items]  
ICC required RTO cost benefit study duration 5 years
Maximum  
Rate And Regulatory Matters [Line Items]  
ICC required RTO cost benefit study duration 10 years
Electric Distribution  
Rate And Regulatory Matters [Line Items]  
Requested Return on Equity Adjustment 0.24%
Number of Proposed Performance Metrics | numberOfProposedPerformanceMetrics 8
Electric Distribution | Minimum  
Rate And Regulatory Matters [Line Items]  
Return on equity adjustment 0.20%
ICC Staff Recommended Return on Equity Adjustment 0.20%
Electric Distribution | Maximum  
Rate And Regulatory Matters [Line Items]  
Return on equity adjustment 0.60%
ICC Staff Recommended Return on Equity Adjustment 0.24%
Pending Rate Case | Electric Distribution | IEIMA  
Rate And Regulatory Matters [Line Items]  
Public Utilities, Requested Rate Increase (Decrease), Amount $ 84
Public Utilities, Requested Equity Capital Structure, Percentage 54.00%
ICC Staff Recommended Rate Increase (Decrease) $ 60
ICC Staff Recommended Equity Capital Structure, Percentage 50.00%
Pending Rate Case | Electric Distribution | FEJA energy-efficiency rider  
Rate And Regulatory Matters [Line Items]  
Public Utilities, Requested Rate Increase (Decrease), Amount $ 17
Pending Rate Case | Natural gas  
Rate And Regulatory Matters [Line Items]  
Natural Gas Capital Investment Prudency Challenge 70
Challenged Recoveries Under the QIP 3
IETL  
Rate And Regulatory Matters [Line Items]  
Energy Transition Assistance Fund Surcharge $ 50