Rate And Regulatory Matters (Narrative-Missouri) (Detail)
$ in Millions
3 Months Ended 7 Months Ended 9 Months Ended 12 Months Ended
Mar. 31, 2021
USD ($)
Sep. 30, 2020
USD ($)
MWh
Sep. 30, 2019
USD ($)
Sep. 30, 2020
USD ($)
Sep. 30, 2020
USD ($)
MWh
Sep. 30, 2019
USD ($)
Dec. 31, 2019
MWh
Dec. 31, 2018
MWh
Rate And Regulatory Matters [Line Items]                
Purchased Power   $ 140 $ 148   $ 383 $ 440    
Other operations and maintenance   418 434   1,240 1,301    
Income Taxes   63 92   134 158    
Donations   0 1   14 8    
Union Electric Company                
Rate And Regulatory Matters [Line Items]                
Purchased Power   48 49   124 160    
Other operations and maintenance   221 242   662 720    
Income Taxes   18 51   29 70    
Donations   $ 0 $ 1   9 3    
Net costs and forgone late fees related to the COVID-19 Pandemic       $ 9        
Final Rate Order | Electricity | Union Electric Company                
Rate And Regulatory Matters [Line Items]                
Public Utilities, Requested Rate Increase (Decrease), Amount         32      
Reduction to annualized base level of net energy costs         115      
Revenues         20      
Purchased Power         15      
Other operations and maintenance         60      
Income Taxes         20      
Revenue requirement change due to MEEIA sales volumes         50      
Amounts previously deferred under PISA         50      
Donations         $ 8      
Wind Generation Facility | Union Electric Company                
Rate And Regulatory Matters [Line Items]                
Amount of Megawatts | MWh   400     300   300 400
Estimated Capital Project Costs         $ 1,200      
Wind Generation Facility | Union Electric Company | Subsequent Event                
Rate And Regulatory Matters [Line Items]                
Project Placed In-Service Amount $ 200              
MEEIA 2019 [Member] | Final Rate Order | Electricity | Union Electric Company                
Rate And Regulatory Matters [Line Items]                
Revenues   $ 6            
Incentive Award if Energy Efficiency Goals Are Achieved         11      
Incentive Award if Energy Efficiency Goals Are Exceeded         1      
MEEIA Energy Efficiency Investments for the 2022 Program Year         $ 70      
MEEIA 2013 & 2016 | Final Rate Order | Electricity | Union Electric Company                
Rate And Regulatory Matters [Line Items]                
Revenues           $ 38    
Minimum | Final Rate Order | Electricity | Union Electric Company                
Rate And Regulatory Matters [Line Items]                
Public Utilities, Requested Return on Equity, Percentage         9.40%      
Maximum | Final Rate Order | Electricity | Union Electric Company                
Rate And Regulatory Matters [Line Items]                
Public Utilities, Requested Return on Equity, Percentage         9.80%