Asset Retirement Obligation $ 691 $ 650 $ 644
Union Electric Company      
Number of Energy Center Scrubbers | scrubber 2    
Postponement of EPA's 2015 Rule two years    
Waste Streams with Postponed Compliance Dates | waste_stream 2    
Number of Energy Centers Constructing Wastewater Treatment Facilities | center 3    
Asset Retirement Obligation $ 687 646 640
Ameren Illinois Company      
Asset Retirement Obligation 4 $ 4 $ 4
Manufactured Gas Plant      
Accrual for environmental loss contingencies $ 129    
Manufactured Gas Plant | Ameren Illinois Company      
Number of remediation sites | site 44    
Accrual for environmental loss contingencies $ 129    
Minimum      
Estimated capital costs to comply with existing and known federal and state air emissions regulations 200    
Minimum | Union Electric Company      
Estimated capital costs to comply with existing and known federal and state air emissions regulations 200    
Minimum | Coal Combustion Residuals Estimate      
Estimated capital costs to comply with existing and known federal and state air emissions regulations 75    
Minimum | Manufactured Gas Plant | Ameren Illinois Company      
Loss contingency, estimate of possible loss 129    
Maximum      
Estimated capital costs to comply with existing and known federal and state air emissions regulations 250    
Maximum | Union Electric Company      
Estimated capital costs to comply with existing and known federal and state air emissions regulations 250    
Maximum | Coal Combustion Residuals Estimate      
Estimated capital costs to comply with existing and known federal and state air emissions regulations 125    
Maximum | Manufactured Gas Plant | Ameren Illinois Company      
Loss contingency, estimate of possible loss 213    
Rush Island Energy Center | Union Electric Company      
Estimated capital costs to comply with preliminary court order 1,000    
Rush Island Energy Center | Minimum | Union Electric Company      
Estimated operations and maintenance costs to comply with preliminary court order. 30    
Rush Island Energy Center | Maximum | Union Electric Company      
Estimated operations and maintenance costs to comply with preliminary court order. 50    
New CCR Rules Estimate      
Asset Retirement Obligation 151    
New CCR Rules Estimate | Union Electric Company      
Asset Retirement Obligation $ 151