XML 57 R42.htm IDEA: XBRL DOCUMENT v3.20.4
Commitments and Contingencies (Tables)
12 Months Ended
Dec. 31, 2020
Commitments and Contingencies  
Schedule of future maturities of long-term debt, finance lease and contractual obligations

Payments due by period

Total

2021

    

2022

    

2023

    

2024

    

2025

    

Thereafter

 

(In thousands)

Long-term debt obligations

$

16,637,809

$

2,027,604

$

2,027,112

$

1,528,030

$

3,027,186

$

2,007,641

$

6,020,236

Interest expense on long-term debt

3,178,253

733,927

$

666,192

$

510,411

$

460,223

$

330,000

$

477,500

Finance lease obligations (1)

162,174

58,379

38,993

35,478

29,324

Interest expense on finance lease obligations (1)

28,084

11,923

9,314

5,464

1,383

Other long-term obligations (2)

4,349,902

350,154

99,048

136,544

173,146

196,000

3,395,010

Operating lease obligations (1)

138,141

71,614

35,074

16,908

9,850

3,205

1,490

Purchase obligations

1,933,440

1,897,777

26,947

8,716

Total

$

26,427,803

$

5,151,378

$

2,902,680

$

2,241,551

$

3,701,112

$

2,536,846

$

9,894,236

(1)See Note 10 for further information on leases and the adoption of ASC 842.
(2)Represents minimum payments related to tower obligations, certain 5G Network Deployment commitments and satellite related and other obligations.
Summary of Wireless Spectrum Licenses

As of

    

December 31, 2020

Build-Out Deadlines

Carrying

Expiration

Amount

Interim

Final

Date

(In thousands)

Owned:

DBS Licenses (1)

$

677,409

700 MHz Licenses

711,871

June 14, 2022 (2)

June 14, 2023 (4)

June 2023

AWS-4 Licenses

1,940,000

June 14, 2022 (2)

June 14, 2023 (4)

June 2023

H Block Licenses

1,671,506

June 14, 2022 (2)

June 14, 2023 (5)

June 2023

600 MHz Licenses

6,211,154

June 14, 2025 (6)

June 2029

MVDDS Licenses (1)

24,000

August 2024

LMDS Licenses (1)

September 2028

28 GHz Licenses

2,883

October 2, 2029 (7)

October 2029

24 GHz Licenses

11,772

December 11, 2029 (7)

December 2029

37 GHz, 39 GHz and 47 GHz Licenses

202,533

June 4, 2030 (7)

June 2030

Subtotal

11,453,128

Non-controlling Investments:

Northstar

5,618,930

October 2021 (3)

October 2027 (8)

October 2027 (8)

SNR

4,271,459

October 2021 (3)

October 2027 (8)

October 2027 (8)

Total AWS-3 Licenses

9,890,389

Capitalized Interest (9)

5,560,422

Total

$

26,903,939

(1)The build-out deadlines for these licenses have been met.
(2)For these licenses, we must offer 5G broadband service to at least 20% of the United States population and have developed a core network by this date.
(3)For these licenses, Northstar Wireless and SNR Wireless must provide reliable signal coverage and offer service to at least 40% of the population of each license area by this date.
(4)For these licenses, we must offer 5G broadband service to 70% of the United States population by this date; provided, however, if by June 14, 2023, we are offering 5G broadband service with respect to these licenses to at least 50% of the population of the United States, the final deadline shall be further extended automatically to June 14, 2025, for us to construct and offer 5G broadband service to at least 70% of the population in each Economic Area (which is a service area established by the FCC) with respect to these licenses.
(5)For these licenses, we must offer 5G broadband service to at least 70% of the United States population by this date; provided, however, that if by June 14, 2023, we are offering 5G Broadband Service with respect to these licenses to at least 50% of the population of the United States, the final deadline shall be further extended automatically to June 14, 2025, for us to construct and offer 5G broadband service to at least 75% of the population in each Economic Area with respect to these licenses.
(6)For these licenses, we must offer 5G broadband service to at least 75% of the population in each Partial Economic Area (which are service areas established by the FCC) by this date.
(7)There are a variety of build-out options and associated build-out metrics associated with these licenses.
(8)For these licenses, Northstar Wireless and SNR Wireless must provide reliable signal coverage and offer service to at least 75% of the population of each license area by this date. If the AWS-3 interim build-out requirement is not met, the AWS-3 expiration date and the AWS-3 final build-out requirement may be accelerated by two years (from October 2027 to October 2025) for each AWS-3 License area in which Northstar Wireless and SNR Wireless do not meet the requirement.
(9)See Note 2 for further information.